13658 W REMINGTON ST 91331
Certificate Information: 13658 W REMINGTON ST 91331
- Application / Permit
- 19016-10000-16658
- Plan Check / Job No.
- B19LA11411
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN (E) 2-CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB-494 AND SB-229.
- Permit Issued
- Issued on 7/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2019 | KEVIN MORALES |
| Corrections Issued | 6/4/2019 | KEVIN MORALES |
| Plan Check Approved | 6/5/2019 | ADAM HEGAZI |
| Issued | 7/2/2019 | LADBS |
| CofO in Progress | 2/6/2020 | MICHEL ABAJAN |
| CofO Issued | 5/11/2020 | MICHAEL SMITH |
| Permit Finaled | 5/11/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/4/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2019 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/7/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/7/2019 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 10/7/2019 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 10/7/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/7/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/18/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/18/2019 | Approved | MICHEL ABAJAN |
| Insulation | 10/23/2019 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/23/2019 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 10/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 11/1/2019 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 11/20/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/18/2019 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/3/2020 | Approved | MICHEL ABAJAN |
| Final | 2/3/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 2/3/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 2/3/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/3/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/3/2020 | Approved | MICHEL ABAJAN |
| Final | 2/5/2020 | OK to Issue CofO | MICHEL ABAJAN |