11828 W GOSHEN AVE 90049
Certificate Information: 11828 W GOSHEN AVE 90049
- Application / Permit
- 19016-10000-16610
- Plan Check / Job No.
- B19LA11387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT STORY RETROFIT AS PER LAMC DIVISION 93. INSTALL TWO (N) STEEL SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofC Issued on 10/13/2022
Permit Application Status History
| Submitted | 6/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2019 | BIDYUT RATH |
| Corrections Issued | 7/9/2019 | BIDYUT RATH |
| Quality Review Completed | 7/11/2019 | SAI KHUM |
| Building Plans Picked Up | 7/12/2019 | APPLICANT |
| Applicant returned to address corrections | 9/17/2019 | BIDYUT RATH |
| Plan Check Approved | 9/23/2019 | BIDYUT RATH |
| No Progress | 10/3/2019 | BIDYUT RATH |
| Plan Check Approved | 11/20/2019 | BIDYUT RATH |
| Issued | 8/9/2021 | APPLICANT |
| OK for CofC | 10/3/2022 | ALAN NOVAK |
| CofC Issued | 10/13/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/4/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Lockwood Builders Inc; Lic. No.: 1016915-A | 9663 SANTA MONICA BLVD #745 BEVERLY HILLS, CA 90210 |
| Engineer | Lara,, Arath Saude; Lic. No.: C68626 | 7778 VALLE VISTA DRIVE RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2021 | Approved | ALAN NOVAK |
| Wood Frame | 12/16/2021 | Partial Approval | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Approved | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Approved | JOHN DODGE |
| Structural Steel Frame | 1/19/2022 | Not Ready for Inspection | JOHN DODGE |
| Interior/Exterior Lathing | 1/24/2022 | Approved | JOHN DODGE |
| Final | 3/3/2022 | Not Ready for Inspection | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Not Ready | JOHN DODGE |
| Smoke Detectors | 3/3/2022 | Not Ready for Inspection | JOHN DODGE |
| Final | 7/1/2022 | Corrections Issued | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 7/1/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 10/3/2022 | OK for CofC | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 10/3/2022 | Approved | ALAN NOVAK |