1437 E PLEASANT AVE 90033

Certificate Information: 1437 E PLEASANT AVE 90033

Application / Permit
19016-10000-16352
Plan Check / Job No.
B19LA11240
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT SINGLE FAMILY DWELLING TO A DUPLEX.
Permit Issued
Issued on 12/24/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/13/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 RAHEL BEYENE
Corrections Issued 6/26/2019 RAHEL BEYENE
Quality Review Completed 7/11/2019 JOSE RODRIGUEZ
Building Plans Picked Up 7/15/2019 APPLICANT
Applicant returned to address corrections 7/30/2019 RAHEL BEYENE
Applicant returned to address corrections 9/27/2019 RAHEL BEYENE
Plan Check Approved 10/23/2019 QUAN NGHIEM
Issued 12/24/2019 LADBS
CofO in Progress 10/23/2020 OSVALDO PARAMO
CofO in Progress 10/23/2020 OSVALDO PARAMO
CofO in Progress 10/23/2020 OSVALDO PARAMO
Permit Finaled 11/13/2020 DEROLD HAUFF
CofO Issued 11/13/2020 DEROLD HAUFF
Permit Finaled 11/13/2020 DEROLD HAUFF

Permit Application Clearance Information

Historic monument Cleared 8/20/2019 MELISSA JONES
Historic monument Cleared 8/20/2019 MELISSA JONES
Address approval Cleared 8/21/2019 KAREN LE
Eng Process Fee Ord 176,300 Cleared 8/21/2019 KAREN LE
Green Code Cleared 8/21/2019 RAHEL BEYENE
Sewer availability Cleared 8/21/2019 KAREN LE
Clean Up Green Up Cleared 9/11/2019 SOPHIE GABEL-SCHEINBAU
Housing rent stabilization Cleared 9/11/2019 MICHAEL GREGERSON

Contact Information

Contractor Owner-Builder       ,
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/31/2019 Conditional Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 12/31/2019 Corrections Issued OSVALDO PARAMO
HVAC-Rough 1/15/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/15/2020 Corrections Issued OSVALDO PARAMO
HVAC-Rough 1/27/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 1/27/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 2/21/2020 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 2/28/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 2/28/2020 Corrections Issued OSVALDO PARAMO
MERV13>=Rough 2/28/2020 Corrections Issued OSVALDO PARAMO
Wood Frame 2/28/2020 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 3/12/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 3/12/2020 Approved OSVALDO PARAMO
HVAC-Rough 3/12/2020 Approved OSVALDO PARAMO
MERV13>=Rough 3/12/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 3/12/2020 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 3/12/2020 Approved OSVALDO PARAMO
Insulation 3/24/2020 Approved OSVALDO PARAMO
Drywall Nailing 4/1/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 4/1/2020 Approved SABAS ALONSO
Final 6/15/2020 Corrections Issued OSVALDO PARAMO
HVAC-Final 6/15/2020 Corrections Issued OSVALDO PARAMO
MERV13>=Final 6/15/2020 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/15/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 6/15/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 8/26/2020 Approved OSVALDO PARAMO
Final 9/14/2020 Corrections Issued OSVALDO PARAMO
MERV13>=Final 9/14/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/14/2020 Not Ready for Inspection OSVALDO PARAMO
Final 9/22/2020 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/22/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 9/22/2020 Approved OSVALDO PARAMO