1437 E PLEASANT AVE 90033
Certificate Information: 1437 E PLEASANT AVE 90033
- Application / Permit
- 19016-10000-16352
- Plan Check / Job No.
- B19LA11240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT SINGLE FAMILY DWELLING TO A DUPLEX.
- Permit Issued
- Issued on 12/24/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | RAHEL BEYENE |
| Corrections Issued | 6/26/2019 | RAHEL BEYENE |
| Quality Review Completed | 7/11/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 7/15/2019 | APPLICANT |
| Applicant returned to address corrections | 7/30/2019 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/27/2019 | RAHEL BEYENE |
| Plan Check Approved | 10/23/2019 | QUAN NGHIEM |
| Issued | 12/24/2019 | LADBS |
| CofO in Progress | 10/23/2020 | OSVALDO PARAMO |
| CofO in Progress | 10/23/2020 | OSVALDO PARAMO |
| CofO in Progress | 10/23/2020 | OSVALDO PARAMO |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic monument | Cleared | 8/20/2019 | MELISSA JONES |
| Historic monument | Cleared | 8/20/2019 | MELISSA JONES |
| Address approval | Cleared | 8/21/2019 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2019 | KAREN LE |
| Green Code | Cleared | 8/21/2019 | RAHEL BEYENE |
| Sewer availability | Cleared | 8/21/2019 | KAREN LE |
| Clean Up Green Up | Cleared | 9/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Housing rent stabilization | Cleared | 9/11/2019 | MICHAEL GREGERSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Niaki,, Neman; Lic. No.: C46030 | 1107 CALIFORNIA AVE #2 SANTA MONICA, CA 90403 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/31/2019 | Conditional Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 12/31/2019 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 1/15/2020 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 1/15/2020 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 1/27/2020 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 1/27/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/21/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/28/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 2/28/2020 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Rough | 2/28/2020 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 2/28/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/12/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/12/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/12/2020 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 3/12/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/12/2020 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/12/2020 | Approved | OSVALDO PARAMO |
| Insulation | 3/24/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/1/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/1/2020 | Approved | SABAS ALONSO |
| Final | 6/15/2020 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 6/15/2020 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Final | 6/15/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/15/2020 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 6/15/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 8/26/2020 | Approved | OSVALDO PARAMO |
| Final | 9/14/2020 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Final | 9/14/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/14/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 9/22/2020 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 9/22/2020 | Approved | OSVALDO PARAMO |