227 E AVENUE 41 90031
Certificate Information: 227 E AVENUE 41 90031
- Application / Permit
- 19016-10000-16342
- Plan Check / Job No.
- B19LA11233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LAMC DIV. 93 . INSTALL THREE OMF.
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/11/2021
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2019 | BIDYUT RATH |
| Corrections Issued | 7/3/2019 | BIDYUT RATH |
| Quality Review Completed | 7/9/2019 | SAI KHUM |
| Building Plans Picked Up | 7/16/2019 | APPLICANT |
| Applicant returned to address corrections | 8/5/2019 | BIDYUT RATH |
| Applicant returned to address corrections | 9/12/2019 | BIDYUT RATH |
| Applicant returned to address corrections | 10/9/2019 | BIDYUT RATH |
| Applicant returned to address corrections | 11/7/2019 | BIDYUT RATH |
| Applicant returned to address corrections | 11/8/2019 | BIDYUT RATH |
| Plan Check Approved | 12/9/2019 | BIDYUT RATH |
| Issued | 2/7/2020 | LADBS |
| OK for CofC | 4/28/2021 | MARK FERRARI |
| CofC Issued | 5/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| HPOZ | Cleared | 8/1/2019 | KATIE DEBIASE |
| Housing rent stabilization | Cleared | 2/5/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/28/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 2/28/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 2/28/2020 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 2/28/2020 | Not Ready for Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 3/3/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 3/6/2020 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 3/6/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 3/9/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 3/11/2020 | Approved | MARK FERRARI |
| Wood Frame | 3/11/2020 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 4/23/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 4/23/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/1/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 8/6/2020 | Corrections Issued | MARK FERRARI |
| Final | 9/24/2020 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 9/24/2020 | Approved | MARK FERRARI |
| Final | 4/20/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/20/2021 | SGSOV Approved | MARK FERRARI |
| Final | 4/28/2021 | OK for CofC | MARK FERRARI |