6814 S AVALON BLVD 90003

Certificate Information: 6814 S AVALON BLVD 90003

Application / Permit
19016-10000-16098
Plan Check / Job No.
B19LA11099
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Homeless Shelter
Work Description
EMERGENCY HOMELESS SHELTER PER GOVERNMENT CODE SECTION 8698.4 AND LAFD DIRECTIVE NO. 45, SECTION II (98 BEDS)
Permit Issued
Issued on 4/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 CAROLYNN NEPOMUCENO
Corrections Issued 6/3/2019 CAROLYNN NEPOMUCENO
Quality Review Completed 6/3/2019 EUGENE BARBEAU
Building Plans Picked Up 6/5/2019 APPLICANT
Disabled Access Plans Picked Up 6/5/2019 APPLICANT
Green Plans Picked Up 6/5/2019 APPLICANT
Applicant returned to address corrections 7/16/2019 CAROLYNN NEPOMUCENO
Plan Check Approved 9/26/2019 CAROLYNN NEPOMUCENO
Issued 4/16/2020 LADBS
TCO Issued (Expire Date: 04-11-2021) 10/13/2020 ERNESTO CORRAL
CofO in Progress 1/8/2021 LEOPOLDO MENDOZA
CofO in Progress 1/8/2021 LEOPOLDO MENDOZA
CofO Issued 1/11/2021 ERNESTO CORRAL
Permit Finaled 1/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

DAS Clearance Cleared 7/11/2019 CAROLYNN NEPOMUCENO
Green Code Cleared 7/11/2019 CAROLYNN NEPOMUCENO
Eng Process Fee Ord 176,300 Cleared 7/17/2019 CELINA MORENO
Sewer availability Cleared 7/17/2019 CELINA MORENO
Project located in CRA area Cleared 7/19/2019 JIM URQUHART
Community Plan Implem. Overlay Cleared 8/14/2019 ALAN COMO
Fire Marshall Fire Life Safety Cleared 9/25/2019 PEJMAN NOORI

Contact Information

Contractor Shipp D; Lic. No.: 969514-B 1160 N COAST HWY      LAGUNA BEACH, CA 92651

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2020 Partial Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 5/1/2020 Partial Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 5/5/2020 Conditional Approval LEOPOLDO MENDOZA
Wood Frame 6/8/2020 Partial Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/10/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 6/10/2020 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/22/2020 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/23/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 6/29/2020 Partial Approval LEOPOLDO MENDOZA
Interior/Exterior Lathing 7/6/2020 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 7/7/2020 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 7/7/2020 Partial Approval LEOPOLDO MENDOZA
Green Building Rough 7/7/2020 Approved LEOPOLDO MENDOZA
Insulation 7/16/2020 Partial Approval LEOPOLDO MENDOZA
Wood Frame 7/16/2020 Approved LEOPOLDO MENDOZA
Drywall Nailing 7/23/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 7/30/2020 Approved LEOPOLDO MENDOZA
Insulation 8/12/2020 Approved LEOPOLDO MENDOZA
Pre-Inspection 8/12/2020 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 9/3/2020 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 9/10/2020 Partial Inspection LEOPOLDO MENDOZA
Pre-Inspection 10/8/2020 Partial Inspection LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 12/22/2020 SGSOV Not Ready LEOPOLDO MENDOZA
Final 12/28/2020 OK to Issue CofO LEOPOLDO MENDOZA
Green Building Final 12/28/2020 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 12/28/2020 SGSOV Approved LEOPOLDO MENDOZA
Smoke Detectors 12/28/2020 Approved LEOPOLDO MENDOZA