565 W 13TH ST 90731
Certificate Information: 565 W 13TH ST 90731
- Application / Permit
- 19016-10000-15456
- Plan Check / Job No.
- B19LA10712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 3HFX PANELS
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- CofC Issued on 1/9/2023
Permit Application Status History
| Submitted | 5/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2019 | THOMAS SHERMAN |
| Corrections Issued | 6/20/2019 | THOMAS SHERMAN |
| Quality Review Completed | 6/25/2019 | SAI KHUM |
| Building Plans Picked Up | 7/8/2019 | APPLICANT |
| Plan Check Approved | 10/1/2019 | THOMAS SHERMAN |
| No Progress | 3/1/2022 | VARAND SARKISIAN |
| Plan Check Approved | 4/4/2022 | VARAND SARKISIAN |
| Issued | 4/6/2022 | APPLICANT |
| OK for CofC | 1/9/2023 | JOEY BUCHANAN |
| CofC Issued | 1/9/2023 | DAVID TSAU |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 8/23/2019 | PHILLIP WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2019 | PHILLIP WILSON |
| Housing rent stabilization | Cleared | 3/3/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2022 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 7/11/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Special/Order Compliance | 8/15/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/20/2022 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 10/20/2022 | No Access for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/9/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 11/9/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 11/16/2022 | Approved | JOEY BUCHANAN |
| Final | 12/7/2022 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 12/7/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 12/29/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 12/29/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 1/9/2023 | OK for CofC | JOEY BUCHANAN |
| Smoke Detectors | 1/9/2023 | Approved | JOEY BUCHANAN |