3438 S KEYSTONE AVE 90034
Certificate Information: 3438 S KEYSTONE AVE 90034
- Application / Permit
- 19016-10000-15364
- Plan Check / Job No.
- B19LA10657
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (2) SCCS.
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- Current Status
- CofC Issued on 7/15/2020
Permit Application Status History
| Submitted | 5/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2019 | VARAND SARKISIAN |
| Corrections Issued | 6/24/2019 | VARAND SARKISIAN |
| Quality Review Completed | 6/25/2019 | SAI KHUM |
| Building Plans Picked Up | 6/27/2019 | APPLICANT |
| Plan Check Approved | 8/1/2019 | VARAND SARKISIAN |
| Issued | 4/28/2020 | APPLICANT |
| OK for CofC | 7/10/2020 | GRANT WOODS |
| CofC Issued | 7/15/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/16/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Brambilla Marco Giovanni; Lic. No.: 544844-B | 109 E HARVARD #306 GLENDALE, CA 91205 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2020 | Approved | PAUL DAVIDSON |
| Deputy Steel/Welding | 5/7/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 5/11/2020 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 5/14/2020 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 5/14/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | SORIN CIRSTOIU |
| Structural Steel Frame | 5/22/2020 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 6/4/2020 | Approved | PAUL DAVIDSON |
| Final | 6/18/2020 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2020 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 6/18/2020 | Not Ready for Inspection | GRANT WOODS |
| Final | 7/10/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 7/10/2020 | Approved | GRANT WOODS |