1049 N MARIPOSA AVE 90029

Certificate Information: 1049 N MARIPOSA AVE 90029

Application / Permit
19016-10000-14756
Plan Check / Job No.
B19LA10270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTAL 4 NEW STEEL CANTILEVER COLUMNS
Permit Issued
Issued on 6/22/2020
Issuing Office
Current Status
CofC Issued on 3/30/2021

Permit Application Status History

Submitted 5/17/2019 APPLICANT
Assigned to Plan Check Engineer 6/19/2019 HANS SANTIAGO
Corrections Issued 6/24/2019 HANS SANTIAGO
Quality Review Completed 6/25/2019 SAI KHUM
Building Plans Picked Up 7/17/2019 APPLICANT
Applicant returned to address corrections 9/11/2019 HANS SANTIAGO
Plan Check Approved 10/4/2019 ANDREW SANTIAGO
Issued 6/22/2020 APPLICANT
OK for CofC 2/11/2021 MARK FERRARI
CofC Issued 3/30/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 6/17/2020 MICHAEL GREGERSON

Contact Information

Contractor Konstruct Inc; Lic. No.: 1037235-B 3964 BIXBY DR      LA VERNE, CA 91750
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2020 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 8/12/2020 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 9/1/2020 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 9/15/2020 Approved MARK FERRARI
Wood Frame 9/21/2020 Corrections Issued MARK FERRARI
Wood Frame 9/29/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 10/6/2020 Corrections Issued MARK FERRARI
Wood Frame 12/11/2020 Approved JONATHAN QUACH
Interior/Exterior Lathing 12/17/2020 Corrections Issued JONATHAN QUACH
Final 1/25/2021 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 1/25/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 1/25/2021 Approved MARK FERRARI
Final 2/11/2021 OK for CofC MARK FERRARI