NON-DUCTILE CONCRETE RETROFIT DIVISON 95 PER ORDINANCE #183893 USING ASCE 7-10. STRUCTURAL UPGRADE ONLY; NO CHANGE OF USE.
Permit Issued
Issued on 9/25/2020
Issuing Office
Metro
Current Status
Issued on 9/25/2020

Permit Application Status History

Submitted 5/16/2019 APPLICANT
Green Plans Picked Up 5/29/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 FARSHAD ALIMOHAMADI
Corrections Issued 6/7/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 6/7/2019 CHARLES CHANG
Disabled Access Plans Picked Up 6/7/2019 APPLICANT
Applicant returned to address corrections 1/23/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/4/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/7/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/3/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/4/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/11/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/22/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/24/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 9/25/2020 FARSHAD ALIMOHAMADI
Issued 9/25/2020 APPLICANT
Building Plans Picked Up 9/28/2020 APPLICANT
Permit Finaled-Status Void 11/3/2023 KATY RAMIREZ
Re-Activate Permit 8/19/2024 KATY RAMIREZ

Permit Application Clearance Information

Green Code Cleared 12/17/2019 KHEDER ALRAZAA
Metro Rail approval Cleared 12/18/2019 FARSHAD ALIMOHAMADI
City Hist. Cultural Monument Cleared 3/13/2020 LAMBERT GIESSINGER
Historic monument Cleared 3/13/2020 LAMBERT GIESSINGER
"Q" conditions Cleared 7/28/2020 CHI DANG
Supp. Use District POD/CDO/TDO Cleared 7/28/2020 CHI DANG
Fire Marshall Fire Life Safety Cleared 8/20/2020 ANDREW KO
DAS Clearance Cleared 8/26/2020 SHINE LIN

Contact Information

Architect Miller,, Jeffrey A; Lic. No.: C37366 448B ROSECRANS AVENUE      MANHATTAN BEACH, CA 90266
Contractor Tectonics Construction Inc; Lic. No.: 705550-B 1005 W 190TH STREET      GARDENA, CA 90248
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2021 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 7/22/2021 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 7/23/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 9/1/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 9/2/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/3/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/9/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/3/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/9/2021 Partial Approval TED RIES
Reinforced Concrete Frame 11/19/2021 Conditional Approval DARRYL ARNOLD
Reinforced Concrete Frame 1/19/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 1/31/2022 Conditional Approval DARRYL ARNOLD
Reinforced Concrete Frame 2/2/2022 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 2/3/2022 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 2/14/2022 Partial Approval KATY RAMIREZ
Wood Frame 2/25/2022 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 5/3/2022 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 5/5/2022 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 6/1/2022 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 6/7/2022 Partial Approval KATY RAMIREZ
Pre-Inspection 10/7/2022 Partial Approval GREGORY POMISH
Final 11/30/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 11/30/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 11/30/2022 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 5/18/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 5/22/2023 Partial Inspection ALFREDO LOPEZ
Drywall Nailing 5/31/2023 Partial Inspection ALFREDO LOPEZ
Light Gage Steel Frame 5/31/2023 Partial Inspection ALFREDO LOPEZ
Final 6/2/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 6/2/2023 Partial Inspection ALFREDO LOPEZ
Pre-Inspection 6/2/2023 Partial Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 6/2/2023 Partial Inspection ALFREDO LOPEZ
Final 7/28/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 7/28/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 7/28/2023 Approved JEROME BLACKWOOD
Final 11/3/2023 Partial Inspection KATY RAMIREZ
Green Building Final 11/3/2023 Approved KATY RAMIREZ
Final 8/19/2024 Partial Inspection WINSTON DUNNING