104 N AVENUE 53 90042
Certificate Information: 104 N AVENUE 53 90042
- Application / Permit
- 19016-10000-14467
- Plan Check / Job No.
- B19LA10042
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 1 OMF AND 1 SCCS.
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- CofC Issued on 10/12/2022
Permit Application Status History
| Submitted | 5/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2019 | JESSE VIDUYA |
| Corrections Issued | 6/19/2019 | JESSE VIDUYA |
| Quality Review Completed | 6/19/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 6/26/2019 | APPLICANT |
| Plan Check Approved | 1/30/2020 | JESSE VIDUYA |
| Issued | 7/7/2021 | APPLICANT |
| OK for CofC | 10/6/2022 | BRUCE CAMPBELL |
| CofC Issued | 10/12/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/10/2019 | ANDREW SANTIAGO |
| Address approval | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| HPOZ | Cleared | 12/30/2019 | KATIE DEBIASE |
| Housing rent stabilization | Cleared | 6/17/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2021 | Corrections Issued | MARK FERRARI |
| Drywall Nailing | 7/14/2021 | Not Ready for Inspection | MARK FERRARI |
| Deputy Steel/Welding | 8/3/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 8/9/2021 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 8/9/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/12/2021 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 8/12/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 8/12/2021 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/16/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 8/17/2021 | Conditional Approval | MARK FERRARI |
| Drywall Nailing | 9/13/2021 | Partial Approval | MARK FERRARI |
| Insulation | 9/13/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 9/13/2021 | Partial Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Pre-Inspection | 6/27/2022 | Corrections Issued | BRUCE CAMPBELL |
| Final | 8/11/2022 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 8/11/2022 | Approved | BRUCE CAMPBELL |
| Final | 8/22/2022 | Corrections Issued | MARK FERRARI |
| Final | 9/8/2022 | Corrections Issued | BRUCE CAMPBELL |
| Final | 10/6/2022 | OK for CofC | BRUCE CAMPBELL |