1312 N CITRUS AVE 90028
Certificate Information: 1312 N CITRUS AVE 90028
- Application / Permit
- 19016-10000-14292
- Plan Check / Job No.
- B19LA09863
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 INSTALL 2 OMF AND 1 HFX PANEL.
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/27/2021
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2019 | EVERARDO SANTOS |
| Corrections Issued | 6/21/2019 | EVERARDO SANTOS |
| Quality Review Completed | 6/25/2019 | SAI KHUM |
| Building Plans Picked Up | 7/22/2019 | APPLICANT |
| Applicant returned to address corrections | 12/18/2019 | EVERARDO SANTOS |
| Plan Check Approved | 11/9/2020 | DANIEL SANJUAN |
| Issued | 3/4/2021 | APPLICANT |
| OK for CofC | 7/26/2021 | MARK FERRARI |
| CofC Issued | 7/27/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 7/25/2019 | JIM URQUHART |
| Miscellaneous | Cleared | 12/18/2019 | RICHARD REASER |
| Historic Resource Verification | Cleared | 11/5/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 11/6/2020 | DAVID URITA |
| Housing rent stabilization | Cleared | 2/25/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Marjanian Hrach; Lic. No.: 559111-B | 6310 WILBUR AVENUE TARZANA, CA 91335 |
| Engineer | Falamaki,, Mohsen; Lic. No.: S3021 | 344 N BUNDY DRIVE LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/16/2021 | Corrections Issued | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 3/31/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/6/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 5/14/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 5/14/2021 | Approved | JONATHAN QUACH |
| Insulation | 5/24/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 5/24/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Interior/Exterior Lathing | 5/26/2021 | Approved | JONATHAN QUACH |
| Final | 6/17/2021 | Conditional Approval | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 6/17/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 6/17/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 6/24/2021 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 6/24/2021 | Not Ready for Inspection | MARK FERRARI |
| Final | 7/26/2021 | OK for CofC | MARK FERRARI |
| Smoke Detectors | 7/26/2021 | Approved | MARK FERRARI |