2191 E WHITTIER BLVD 90023
Certificate Information: 2191 E WHITTIER BLVD 90023
- Application / Permit
- 19016-10000-14211
- Plan Check / Job No.
- B19LA09788
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TI AND CHANGE OF USE FROM RETAIL TO RESTAURANT HOURS OF OPERATION LIMITED TO 7AM TO 11PM
- Permit Issued
- Issued on 9/30/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 6/5/2019 | EMMANUEL MARTINEZ |
| Disabled Access Plans Picked Up | 6/13/2019 | APPLICANT |
| Quality Review Completed | 6/17/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 6/26/2019 | APPLICANT |
| Applicant returned to address corrections | 8/13/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 9/12/2019 | EMMANUEL MARTINEZ |
| Issued | 9/30/2019 | LADBS |
| CofO in Progress | 1/7/2025 | RONALD JIMENEZ |
| CofO Issued | 1/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 8/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Comm Cor/Mini-Mall | Cleared | 8/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Comm Cor/Mini-Mall | Cleared | 8/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Comm Cor/Mini-Mall | Cleared | 8/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Project located in CRA area | Cleared | 8/13/2019 | JIM URQUHART |
| ZI | Cleared | 8/13/2019 | SOPHIE GABEL-SCHEINBAU |
| Address approval | Cleared | 9/5/2019 | JAMES MORALEZ |
| DAS Clearance | Cleared | 9/5/2019 | EMMANUEL MARTINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2019 | JAMES MORALEZ |
| Food Service Establishment | Cleared | 9/5/2019 | THEODORE HIGGINS |
| Sewer availability | Cleared | 9/5/2019 | JAMES MORALEZ |
| ZA Case | Cleared | 9/5/2019 | ANNA VAN |
| Food establishment approval | Cleared | 9/12/2019 | LACDHS APPROVED |
Contact Information
| Architect | Cline,, Daniel Lee; Lic. No.: C19518 | 18572 AVOLINDA DRIVE YORBA LINDA, CA 92886 |
| Contractor | Willis Construction Company; Lic. No.: 1020831-B | 15138 ELMBROOK DR LA MIRADA, CA 90638 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/15/2019 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 10/18/2019 | Approved | JEFFREY FULTON |
| Drywall Nailing | 10/28/2019 | Approved | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2019 | Approved | JEFFREY FULTON |
| Pre-Inspection | 11/5/2019 | Corrections Issued | JEFFREY FULTON |
| Footing/Foundation/Slab | 11/8/2019 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 12/9/2019 | Partial Inspection | JEFFREY FULTON |
| Final | 3/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Final | 3/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Rough | 3/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 3/6/2020 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 3/6/2020 | Approved | RONALD PACHECO |
| Wood Frame | 3/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 5/31/2024 | Corrections Issued | RONALD JIMENEZ |
| METHANE-Final | 5/31/2024 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 5/31/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 5/31/2024 | Approved | RONALD JIMENEZ |
| Final | 1/7/2025 | OK to Issue CofO | RONALD JIMENEZ |