1015 W 39TH ST 90037
Certificate Information: 1015 W 39TH ST 90037
- Application / Permit
- 19016-10000-13849
- Plan Check / Job No.
- B19LA09513
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 SCCS
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/29/2023
Permit Application Status History
| Submitted | 5/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2019 | JESSE VIDUYA |
| Corrections Issued | 5/25/2019 | JESSE VIDUYA |
| Quality Review Completed | 5/29/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 5/31/2019 | APPLICANT |
| Applicant returned to address corrections | 6/11/2019 | JESSE VIDUYA |
| Plan Check Approved | 6/13/2019 | JESSE VIDUYA |
| No Progress | 5/11/2023 | VARAND SARKISIAN |
| Plan Check Approved | 5/11/2023 | VARAND SARKISIAN |
| Issued | 6/7/2023 | APPLICANT |
| OK for CofC | 8/28/2023 | DARRYL ARNOLD |
| CofC Issued | 8/29/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 6/11/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | CELINA MORENO |
| Project located in CRA area | Cleared | 6/13/2019 | JIM URQUHART |
| ZI | Cleared | 6/13/2019 | SARAHI ORTEGA |
| Housing rent stabilization | Cleared | 5/15/2023 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Neptune Construction & Remodeling Inc; Lic. No.: 902661-B | 5816 LANKERCHIM BLVD #4 NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2023 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 7/5/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 7/12/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/14/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 7/14/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/17/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 7/17/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 7/17/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/19/2023 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 7/19/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/19/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/8/2023 | Approved | DARRYL ARNOLD |
| Final | 8/17/2023 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/17/2023 | Approved | DARRYL ARNOLD |
| Final | 8/28/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/28/2023 | Approved | DARRYL ARNOLD |