11324 W HUSTON ST 91601

Certificate Information: 11324 W HUSTON ST 91601

Application / Permit
19016-10000-13755
Plan Check / Job No.
B19LA09453
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 1 STEEL CANTILEVER COLUMN
Permit Issued
Issued on 1/15/2021
Issuing Office
Current Status
CofC Issued on 8/25/2021

Permit Application Status History

Submitted 5/9/2019 APPLICANT
Assigned to Plan Check Engineer 5/22/2019 HANS SANTIAGO
Corrections Issued 5/28/2019 HANS SANTIAGO
Quality Review Completed 5/29/2019 SAI KHUM
Building Plans Picked Up 5/30/2019 APPLICANT
Applicant returned to address corrections 7/11/2019 HANS SANTIAGO
Plan Check Approved 7/18/2019 ANDREW SANTIAGO
Issued 1/15/2021 APPLICANT
OK for CofC 8/13/2021 JOE VELASQUEZ
CofC Issued 8/25/2021 JEFFREY DURAN

Permit Application Clearance Information

Project located in CRA area Cleared 7/12/2019 JIM URQUHART
Housing rent stabilization Cleared 1/8/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Par Construction Inc; Lic. No.: 983593-B 12319 GREENE AVE      LOS ANGELES, CA 90066
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 6/29/2021 No Access for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/1/2021 No Access for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 7/1/2021 No Access for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/12/2021 No Access for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 7/12/2021 No Access for Inspection JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/14/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/14/2021 Not Ready for Inspection JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/15/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/15/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/26/2021 Corrections Issued JOE VELASQUEZ
Structural Steel Frame 7/26/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/26/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/27/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/27/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/28/2021 Conditional Approval JOE VELASQUEZ
Structural Steel Frame 7/28/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/28/2021 Approved JOE VELASQUEZ
Deputy Reinf. Concrete 7/29/2021 No Access for Inspection JOE VELASQUEZ
Insulation 7/29/2021 Conditional Approval JOE VELASQUEZ
Interior/Exterior Lathing 8/2/2021 Conditional Approval JOE VELASQUEZ
Final 8/13/2021 OK for CofC JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved JOE VELASQUEZ
Smoke Detectors 8/13/2021 Approved JOE VELASQUEZ