11324 W HUSTON ST 91601
Certificate Information: 11324 W HUSTON ST 91601
- Application / Permit
- 19016-10000-13755
- Plan Check / Job No.
- B19LA09453
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 1 STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- CofC Issued on 8/25/2021
Permit Application Status History
| Submitted | 5/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2019 | HANS SANTIAGO |
| Corrections Issued | 5/28/2019 | HANS SANTIAGO |
| Quality Review Completed | 5/29/2019 | SAI KHUM |
| Building Plans Picked Up | 5/30/2019 | APPLICANT |
| Applicant returned to address corrections | 7/11/2019 | HANS SANTIAGO |
| Plan Check Approved | 7/18/2019 | ANDREW SANTIAGO |
| Issued | 1/15/2021 | APPLICANT |
| OK for CofC | 8/13/2021 | JOE VELASQUEZ |
| CofC Issued | 8/25/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 7/12/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 1/8/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Par Construction Inc; Lic. No.: 983593-B | 12319 GREENE AVE LOS ANGELES, CA 90066 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 6/29/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/1/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/1/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/12/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/12/2021 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/26/2021 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 7/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/28/2021 | Conditional Approval | JOE VELASQUEZ |
| Structural Steel Frame | 7/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/28/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/29/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 7/29/2021 | Conditional Approval | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/2/2021 | Conditional Approval | JOE VELASQUEZ |
| Final | 8/13/2021 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 8/13/2021 | Approved | JOE VELASQUEZ |