2113 S PROSSER AVE 90025
Certificate Information: 2113 S PROSSER AVE 90025
- Application / Permit
- 19016-10000-13584
- Plan Check / Job No.
- B19LA09345
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU PER AB 494 AND SB 229 PER WFPP TYPE V
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2019 | ADAM HEGAZI |
| Corrections Issued | 5/8/2019 | ADAM HEGAZI |
| Applicant returned to address corrections | 7/13/2021 | KHUONG TRUONG |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 4/4/2023 | STEPHANIE SWANSON |
| Permit Finaled | 4/7/2023 | DANIEL ORRANTE |
| CofO Issued | 4/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 5/12/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 5/12/2021 | SAUL GARCIA |
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2022 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 5/12/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/11/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 7/11/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 7/11/2022 | Not Ready for Inspection | HERBERT GIRON |
| METHANE-Rough | 7/11/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 7/11/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 9/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 9/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/9/2022 | Approved | STEPHANIE SWANSON |
| Gas Test | 9/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 9/15/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/15/2022 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 9/15/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/16/2022 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 9/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 9/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 9/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 11/8/2022 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 11/8/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/14/2022 | Conditional Approval | STEPHANIE SWANSON |
| Green Building Rough | 11/14/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/8/2022 | Approved | STEPHANIE SWANSON |
| Sewer | 12/8/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/17/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 3/17/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 3/17/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 3/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/17/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 3/17/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/4/2023 | Approved | STEPHANIE SWANSON |
| Final | 4/4/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| HVAC-Final | 4/4/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 4/4/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Approved | STEPHANIE SWANSON |