201 N CARMELINA AVE 90049
Certificate Information: 201 N CARMELINA AVE 90049
- Application / Permit
- 19016-10000-13546
- Plan Check / Job No.
- B19LA09329
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- REMODEL OF (E) ACCESSORY LIVING QUARTERS, REMOVE AND REPLACE ROOF FRAMING. REMOVE 14'-10" X 15'-0" AREA.
- Permit Issued
- Issued on 8/19/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | ROSENDO MEDINA |
| Corrections Issued | 6/28/2019 | ROSENDO MEDINA |
| Quality Review Completed | 7/1/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2019 | APPLICANT |
| Plan Check Approved | 8/14/2019 | ROSENDO MEDINA |
| Issued | 8/19/2019 | LADBS |
| CofO in Progress | 11/4/2024 | ARAM AVEDISIAN |
| No Progress | 12/2/2024 | KENNETH NAGLE |
| CofO in Progress | 12/2/2024 | KENNETH NAGLE |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
| CofO Issued | 12/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2019 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 7/11/2019 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 7/11/2019 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 7/11/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/11/2019 | ADRIAN SANCHEZ |
Contact Information
| Architect | Hefner,, William Robert; Lic. No.: C17013 | 5820 WILSHIRE BLVD SUITE 500 LOS ANGELES, CA 90036 |
| Contractor | T M C General Contractors Inc; Lic. No.: 603053-B | 15415 SUNSET BLVD SUITE 1 PACIFIC PALISADES, CA 90272 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 1386 EAST WALNUT STREET SUITE 202 PASADENA, CA 91106 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 1/10/2020 | Partial Approval | DANNY TOLENTINO |
| Deputy Drilled-In Anchors | 1/14/2020 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/15/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 1/24/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 2/10/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 7/11/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/3/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 11/3/2022 | Partial Approval | JUAN VALENZUELA |
| Special/Order Compliance | 11/3/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/16/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 12/12/2022 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 12/12/2022 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 3/8/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/18/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/27/2023 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 8/15/2023 | Partial Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/2/2023 | Partial Approval | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 10/2/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 10/12/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 10/18/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/7/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/29/2024 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/12/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 2/12/2024 | Approved | KEVIN SARGSYAN |
| Gas Test | 3/11/2024 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 3/11/2024 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 3/13/2024 | Approved | DANIEL ORRANTE |
| PLUMBING-Rough | 3/21/2024 | Approved | KEVIN SARGSYAN |
| Sewer | 3/21/2024 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 4/11/2024 | Partial Inspection | KEVIN SARGSYAN |
| Sewer | 4/22/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/11/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/23/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/23/2024 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/23/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/26/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 8/26/2024 | Approved | KEVIN SARGSYAN |
| Final | 10/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 10/7/2024 | Approved | KEVIN SARGSYAN |
| Final | 11/4/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Special/Order Compliance | 11/27/2024 | Corrections Issued | KENNETH NAGLE |
| Special/Order Compliance | 12/2/2024 | Conditional Approval | KENNETH NAGLE |