916 S PATTON AVE 90731
Certificate Information: 916 S PATTON AVE 90731
- Application / Permit
- 19016-10000-13374
- Plan Check / Job No.
- B19LA09206
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAME.
- Permit Issued
- Issued on 7/23/2021
- Issuing Office
- Current Status
- Issued on 7/23/2021
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | MANUEL MONTUFAR |
| Corrections Issued | 5/30/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 6/3/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/18/2019 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 11/4/2019 | MANUEL MONTUFAR |
| Plan Check Approved | 11/7/2019 | MANUEL MONTUFAR |
| Issued | 7/23/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | JEANIE LAM |
| Work Adjacent to Public Way | Cleared | 11/6/2019 | BOK GOH |
| Housing rent stabilization | Cleared | 4/30/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | M A F Construction Inc; Lic. No.: 540983-B | 1000 N WESTERN AVENUE STE 201 SAN PEDRO, CA 90732 |
| Engineer | Givechi,, Mehrzad; Lic. No.: C45725 | 344 VIA COLUSA REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/23/2021 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/25/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 10/12/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/4/2021 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 11/4/2021 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 12/2/2021 | Approved | JOEY BUCHANAN |
| Final | 12/16/2021 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV No Gas | JOEY BUCHANAN |
| Smoke Detectors | 12/16/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 3/24/2025 | Corrections Issued | MICHAEL PETRUSKO |
| Smoke Detectors | 3/24/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |