2129 N WOLLAM ST 90065
Certificate Information: 2129 N WOLLAM ST 90065
- Application / Permit
- 19016-10000-13216
- Plan Check / Job No.
- B19LA09104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE EXISTING SFD BY CONVERTING PART OF UNCONDITIONED BASEMENT SPACE TO HABITABLE SPACE. INTERIOR RENOVATION OF SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/4/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | KEVIN MORALES |
| Corrections Issued | 5/29/2019 | KEVIN MORALES |
| Quality Review Completed | 6/10/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 9/20/2019 | APPLICANT |
| Plan Check Approved | 1/4/2023 | KEVIN MORALES |
| Issued | 12/4/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 8/30/2019 | JEANETTE VONG |
| GPI Written Notices | Cleared | 9/16/2022 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 9/16/2022 | KEVIN MORALES |
| Green Code | Cleared | 9/16/2022 | KEVIN MORALES |
| Specific Plan | Cleared | 12/21/2022 | JASON CHAN |
Contact Information
| Contractor | Whitcomb Hughes Design & Build; Lic. No.: 1067597-B | 1443 E WASHINGTON BLVD #287 PASADENA, CA 91104 |
| Engineer | Vanik, Abedian; Lic. No.: S5323 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Corrections Issued | ROY SPAULDING |
| Deputy Drilled-In Anchors | 12/27/2023 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/24/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/12/2024 | No Access for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/15/2024 | Approved | HAMIK HARTOUNIAN |
| Sewer | 4/17/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 8/1/2024 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/4/2024 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/18/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/18/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 10/23/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/23/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/7/2025 | Approved | NICHOLAS LOPEZ |
| Gas Test | 3/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| Green Building Rough | 3/7/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 3/7/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 3/10/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Conditional Approval | BRENDAN MORELLI |
| Drywall Nailing | 3/17/2025 | Approved | REGINA MENDEZ |
| Green Building Rough | 3/17/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/9/2025 | Approved | NICHOLAS LOPEZ |
| Final | 7/23/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 7/23/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 7/23/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 7/23/2025 | Approved | NICHOLAS LOPEZ |