14638 W KITTRIDGE ST 91405
Certificate Information: 14638 W KITTRIDGE ST 91405
- Application / Permit
- 19016-10000-13024
- Plan Check / Job No.
- B19LA08947
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 3 SCCS AND 3 SIMPSON STRONG WALLS
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/3/2020
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2019 | EVERARDO SANTOS |
| Corrections Issued | 5/20/2019 | EVERARDO SANTOS |
| Quality Review Completed | 5/20/2019 | SAI KHUM |
| Building Plans Picked Up | 5/21/2019 | APPLICANT |
| Plan Check Approved | 6/28/2019 | EVERARDO SANTOS |
| No Progress | 12/20/2019 | EVERARDO SANTOS |
| Plan Check Approved | 12/20/2019 | EVERARDO SANTOS |
| Issued | 3/4/2020 | LADBS |
| OK for CofC | 7/1/2020 | DANIEL VARNUM |
| CofC Issued | 8/3/2020 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/2/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Alam,, Anwar; Lic. No.: S5719 | 372 FLORAL VIEW IRVINE, CA 92618 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2020 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 4/9/2020 | Approved | HAMID PISHEHVAR |
| Excavation/Setback/Form/Re-Bar | 4/10/2020 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 4/13/2020 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 4/13/2020 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 4/20/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/21/2020 | Conditional Approval | DANIEL VARNUM |
| Final | 4/22/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Smoke Detectors | 4/22/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 4/22/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/21/2020 | Approved | DANIEL VARNUM |
| Final | 7/1/2020 | OK for CofC | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 7/1/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 7/1/2020 | Approved | DANIEL VARNUM |
| Final | 7/6/2020 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 7/6/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 7/6/2020 | Approved | DANIEL VARNUM |