244 S RENO ST 90057
Certificate Information: 244 S RENO ST 90057
- Application / Permit
- 19016-10000-12925
- Plan Check / Job No.
- B19LA08889
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 1 SHEAR WALLS AND 5 SCCS.
- Permit Issued
- Issued on 4/23/2024
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/11/2026
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2019 | EVERARDO SANTOS |
| Corrections Issued | 6/4/2019 | EVERARDO SANTOS |
| Quality Review Completed | 6/4/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 6/5/2019 | APPLICANT |
| Plan Check Approved | 7/3/2019 | EVERARDO SANTOS |
| Issued | 4/23/2024 | APPLICANT |
| OK for CofC | 2/11/2026 | DARRYL ARNOLD |
| CofC Issued | 2/11/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/7/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Twenty One Retrofit Inc; Lic. No.: 1065687-B | 17700 S AVALON BLVD UNIT #345 CARSON, CA 90746 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/14/2024 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 5/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/31/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 6/6/2024 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 6/13/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 7/16/2024 | Conditional Approval | JEROME BLACKWOOD |
| METHANE-Final | 7/16/2024 | Approved | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 7/16/2024 | Approved | JEROME BLACKWOOD |
| Final | 2/11/2026 | OK for CofC | DARRYL ARNOLD |