2738 W LOCKSLEY PL 90039

Certificate Information: 2738 W LOCKSLEY PL 90039

Application / Permit
19016-10000-12917
Plan Check / Job No.
B19LA08885
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
REMOVE ALL EXTERIOR WALS OF A ONE CAR GARAGE EXCEPT 9 LF AT SOUTH PORTION OF THE WALL AND BUILT A NEW 36'6" X 12' ONE CAR GARAGE , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 RARES BODEA
Corrections Issued 6/9/2019 RARES BODEA
Quality Review Completed 6/11/2019 OMID HEDAYAT
Green Plans Picked Up 6/14/2019 APPLICANT
Building Plans Picked Up 6/20/2019 APPLICANT
Applicant returned to address corrections 1/8/2020 RARES BODEA
Plan Check Approved 1/15/2020 RARES BODEA
Issued 1/17/2020 LADBS
CofO in Progress 11/2/2021 THOMAS LOGRASSO
Permit Finaled 11/5/2021 DEROLD HAUFF
CofO Issued 11/5/2021 DEROLD HAUFF
Permit Finaled 11/5/2021 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/7/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/7/2019 JEANIE LAM
BHO/Hillside ordinance Cleared 12/18/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 12/18/2019 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 12/19/2019 PATRICK MISCHLICH
Low Impact Development Cleared 12/19/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/23/2019 EMIL KYUPELYAN
Green Code Cleared 12/30/2019 RARES BODEA
GPI Written Notices Cleared 1/8/2020 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 184 S ALTADENA DRIVE      PASADENA, CA 91107

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2020 Approved AJA COLLAY
Footing/Foundation/Slab 4/27/2020 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/6/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/6/2020 Approved STUART CHAPMAN
Green Building Rough 8/26/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 8/26/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 12/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 12/4/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Approved SCOTT FINNILA
Green Building Rough 12/18/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 12/18/2020 Partial Approval SCOTT FINNILA
Wood Frame 12/18/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 2/10/2021 Partial Approval HAMIK HARTOUNIAN
Final 6/3/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 6/3/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 6/3/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 6/8/2021 Corrections Issued KATHRYN BUTTERWORTH
Final 10/26/2021 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 10/26/2021 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 10/26/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 11/1/2021 OK to Issue CofO THOMAS LOGRASSO
Smoke Detectors 11/1/2021 Approved THOMAS LOGRASSO