4490 N HAZELTINE AVE 91423
Certificate Information: 4490 N HAZELTINE AVE 91423
- Application / Permit
- 19016-10000-12870
- Plan Check / Job No.
- B19LA08857
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 1 SCCS.
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/28/2023
Permit Application Status History
| Submitted | 5/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2019 | JESSE VIDUYA |
| Corrections Issued | 6/3/2019 | JESSE VIDUYA |
| Quality Review Completed | 6/5/2019 | SAI KHUM |
| Building Plans Picked Up | 6/28/2019 | APPLICANT |
| Plan Check Approved | 9/11/2019 | JESSE VIDUYA |
| Issued | 7/15/2022 | APPLICANT |
| OK for CofC | 10/23/2023 | KENNETH ROBERTS |
| CofC Issued | 12/28/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/18/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lara,, Arath Saude; Lic. No.: C68626 | 7778 VALLE VISTA DRIVE RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2023 | Approved | KENNETH ROBERTS |
| Wood Frame | 5/2/2023 | Partial Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Corrections Issued | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 7/26/2023 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 7/26/2023 | Conditional Approval | KENNETH ROBERTS |
| Deputy Wood Construction | 7/26/2023 | Conditional Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Footing/Foundation/Slab | 7/31/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Structural Steel Frame | 7/31/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Wood Frame | 7/31/2023 | Not Ready for Inspection | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Approved | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 9/12/2023 | Approved | KENNETH ROBERTS |
| Wood Frame | 9/12/2023 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 9/18/2023 | Conditional Approval | STEVEN LEVITT |
| Drywall Nailing | 10/4/2023 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 10/6/2023 | Approved | KENNETH ROBERTS |
| Final | 10/23/2023 | OK for CofC | KENNETH ROBERTS |