1162 N GLENDALE BLVD 90026
Certificate Information: 1162 N GLENDALE BLVD 90026
- Application / Permit
- 19016-10000-12679
- Plan Check / Job No.
- B19LA08731
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- Change of use from medical office to bakery. OPRATION FROM 7AM TO 11PM.
- Permit Issued
- Issued on 8/26/2019
- Issuing Office
- Metro
- Current Status
- Permit Closed on 8/14/2024
- Certificate of Occupancy
- Permit Closed More Information
Permit Application Status History
Submitted | 4/30/2019 | APPLICANT |
Assigned to Plan Check Engineer | 5/16/2019 | SHANGQIN XIE |
Corrections Issued | 5/22/2019 | SHANGQIN XIE |
Quality Review Completed | 5/30/2019 | KESETE HAREGOT |
Building Plans Picked Up | 5/31/2019 | APPLICANT |
Disabled Access Plans Picked Up | 6/17/2019 | APPLICANT |
Applicant returned to address corrections | 8/19/2019 | SHANGQIN XIE |
Plan Check Approved | 8/21/2019 | SHANGQIN XIE |
Issued | 8/26/2019 | LADBS |
Permit Closed | 8/14/2024 | RONALD JIMENEZ |
Permit Closed | 8/14/2024 | RONALD JIMENEZ |
Permit Application Clearance Information
Comm Cor/Mini-Mall | Cleared | 6/4/2019 | ANNA VAN |
Eng Process Fee Ord 176,300 | Cleared | 6/4/2019 | ELENA LOPEZ |
Sewer availability | Cleared | 6/4/2019 | ELENA LOPEZ |
ZA Case | Cleared | 6/4/2019 | ANNA VAN |
"Q" conditions | Cleared | 6/6/2019 | ANNA VAN |
Supp. Use District POD/CDO/TDO | Cleared | 6/6/2019 | MONIQUE ACOSTA |
DAS Clearance | Cleared | 8/14/2019 | CHOI YAN |
Food establishment approval | Cleared | 8/19/2019 | LACDHS APPROVED |
Contact Information
Architect | Jeffrey, Miller; Lic. No.: C37366 | , |
Contractor | Owner-Builder | , |
Inspector Information
JULIAN CAPUCETTI, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 9/5/2019 | Approved | KATY RAMIREZ |
Excavation/Setback/Form/Re-Bar | 9/20/2019 | Partial Approval | KATY RAMIREZ |
Wood Frame | 11/6/2019 | Partial Inspection | JEFFREY FULTON |
Wood Frame | 2/5/2021 | Not Ready for Inspection | RONALD PACHECO |
Final | 8/14/2024 | Permit Closed | RONALD JIMENEZ |
SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Not Ready | RONALD JIMENEZ |
Smoke Detectors | 8/14/2024 | Permit Closed | RONALD JIMENEZ |