3836 S KEYSTONE AVE 90232
Certificate Information: 3836 S KEYSTONE AVE 90232
- Application / Permit
- 19016-10000-12544
- Plan Check / Job No.
- B19LA08619
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 4 NEW SCCS AND SHEARWALL.
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Metro
- Current Status
- OK for CofC on 11/10/2022
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | REZA HAGHIGHAT |
| Corrections Issued | 5/13/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 5/15/2019 | SAI KHUM |
| Building Plans Picked Up | 5/20/2019 | APPLICANT |
| Plan Check Approved | 8/17/2022 | REZA HAGHIGHAT |
| Issued | 8/22/2022 | APPLICANT |
| OK for CofC | 11/4/2022 | PAUL DAVIDSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/26/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Lupu Iancu; Lic. No.: 580850-B | 1420 NORTH ALTA VISTA #213 LOS ANGELES, CA 90046 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2022 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 9/30/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/3/2022 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/3/2022 | Conditional Approval | GRANT WOODS |
| Deputy Wood Construction | 10/3/2022 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Approved | GRANT WOODS |
| Structural Steel Frame | 10/5/2022 | Approved | GRANT WOODS |
| Wood Frame | 10/5/2022 | Partial Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 10/25/2022 | Approved | GRANT WOODS |
| Final | 11/4/2022 | OK for CofC | PAUL DAVIDSON |
| METHANE-Final | 11/4/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 11/4/2022 | Approved | PAUL DAVIDSON |