2725 W VERNON AVE 90008

Certificate Information: 2725 W VERNON AVE 90008

Application / Permit
19016-10000-12374
Plan Check / Job No.
B19LA08534
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) STRONG WALLS FOR A MIXED USE BUILDING (APT/RETAIL)
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
OK for CofC on 12/14/2022

Permit Application Status History

Submitted 4/26/2019 APPLICANT
Application Withdrawn 4/26/2019 APPLICANT
Re-Activate Applicaton 4/26/2019 APPLICANT
Assigned to Plan Check Engineer 5/8/2019 JESSE VIDUYA
Corrections Issued 5/11/2019 JESSE VIDUYA
Quality Review Completed 5/14/2019 HANS SANTIAGO
Building Plans Picked Up 5/15/2019 APPLICANT
Disabled Access Plans Picked Up 6/6/2019 APPLICANT
Applicant returned to address corrections 9/23/2019 JESSE VIDUYA
Plan Check Approved 9/27/2019 JESSE VIDUYA
Plan Check Approved 10/5/2020 JESSE VIDUYA
Issued 11/4/2020 APPLICANT
OK for CofC 12/13/2022 DARRYL ARNOLD
CofC Issued 12/13/2022 WINSTON DUNNING
OK for CofC 12/13/2022 DARRYL ARNOLD

Permit Application Clearance Information

DAS Clearance Cleared 9/17/2019 ELIZABETH TOMS
ZI Cleared 9/25/2019 KYLE WINSTON
Housing rent stabilization Cleared 10/29/2020 MICHAEL SOTO

Contact Information

Contractor Dotz Inc; Lic. No.: 1033830-B 17321 MURPHY AVE #240      IRVINE, CA 92614
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/21/2021 Conditional Approval MARK FERRARI
Structural Steel Frame 4/21/2021 Conditional Approval MARK FERRARI
Wood Frame 4/21/2021 Not Ready for Inspection MARK FERRARI
Wood Frame 5/14/2021 Corrections Issued JOEY BUCHANAN
Structural Steel Frame 5/17/2021 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 6/1/2021 Corrections Issued MARK FERRARI
Drywall Nailing 2/2/2022 Conditional Approval DARRYL ARNOLD
Final 3/22/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/22/2022 Approved DARRYL ARNOLD
Final 7/12/2022 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Not Ready DARRYL ARNOLD
Final 8/15/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Not Ready DARRYL ARNOLD
Final 8/18/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready DARRYL ARNOLD
Final 10/4/2022 Not Ready for Inspection BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 10/4/2022 SGSOV Not Ready BRUCE CAMPBELL
Final 11/7/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Not Ready DARRYL ARNOLD
Final 12/13/2022 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved DARRYL ARNOLD