841 S MUIRFIELD ROAD 90005
Certificate Information: 841 S MUIRFIELD ROAD 90005
- Application / Permit
- 19016-10000-12000
- Plan Check / Job No.
- B19LA08281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE (360SQFT) AND WORK SHOP (228SQFT) BLDG. INTO A.D.U. (648SQFT) PER STATE LAW ***FIRE SPRINKLER 13D REQUIRED, SINCE (E) SFD REQUIRED UNDER: 21014-10000-06120*** SEE COMMETNS
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/26/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/12/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/21/2019 | CRISTINA SALAZAR |
| Plan Check Approved | 8/21/2019 | LUKE GONZALES |
| Issued | 2/2/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | JEFFREY MEAD |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
| CofO Issued | 3/16/2025 | DEROLD HAUFF |
| Permit Finaled | 3/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/15/2019 | RIDWAN HARDY |
| Address approval | Cleared | 8/21/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 8/21/2019 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2024 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/29/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/26/2024 | Corrections Issued | JEFFREY MEAD |
| Sewer | 4/26/2024 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 4/26/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/28/2024 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 6/6/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 8/13/2024 | Approved | JOSH MEISTER |
| Insulation | 8/13/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 8/13/2024 | Partial Approval | JOSH MEISTER |
| Shower Pan | 8/13/2024 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/20/2024 | Conditional Approval | JOSE MACIAS |
| HVAC-Rough | 9/20/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 9/20/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 9/25/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/21/2025 | Approved | JEFFREY MEAD |
| Final | 2/21/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 2/21/2025 | Approved | JEFFREY MEAD |
| METHANE-Final | 2/21/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 2/21/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 2/21/2025 | Approved | JEFFREY MEAD |
| Final | 2/26/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/10/2025 | OK to Issue CofO | JEFFREY MEAD |