5192 W 20TH ST 90016
Certificate Information: 5192 W 20TH ST 90016
- Application / Permit
- 19016-10000-11999
- Plan Check / Job No.
- B19LA08280
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (1) SHEAR WALL AND (1) SCCS
- Permit Issued
- Issued on 5/7/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/17/2023
Permit Application Status History
| Submitted | 4/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2019 | EVERARDO SANTOS |
| Corrections Issued | 5/28/2019 | EVERARDO SANTOS |
| Quality Review Completed | 5/30/2019 | SAI KHUM |
| Building Plans Picked Up | 5/31/2019 | APPLICANT |
| Applicant returned to address corrections | 7/22/2019 | EVERARDO SANTOS |
| Plan Check Approved | 9/16/2019 | EVERARDO SANTOS |
| Issued | 5/7/2020 | LADBS |
| OK for CofC | 8/21/2020 | DARRYL ARNOLD |
| CofC Issued | 8/17/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/31/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/4/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/22/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 6/23/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 6/23/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/23/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/24/2020 | Partial Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/25/2020 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 6/26/2020 | Partial Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/2/2020 | Approved | FELIX CEBALLOS |
| Final | 8/21/2020 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/21/2020 | Approved | DARRYL ARNOLD |