1014 W DEL RIO AVE 90065
Certificate Information: 1014 W DEL RIO AVE 90065
- Application / Permit
- 19016-10000-11823
- Plan Check / Job No.
- B19LA08157
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING 2 CAR GARAGE INTO AN ADU PER AB494 and SB229 AND ATTACHED DECK.
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2019 | ZAW HAN |
| Corrections Issued | 4/23/2019 | ZAW HAN |
| Plan Check Approved | 5/7/2019 | KEVIN MORALES |
| Issued | 2/14/2020 | LADBS |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| CofO in Progress | 8/4/2020 | HAMIK HARTOUNIAN |
| No Progress | 9/4/2020 | ELMER BLAND |
| CofO in Progress | 9/24/2020 | RONALD MYRICK |
| CofO Issued | 9/24/2020 | RONALD MYRICK |
| Permit Finaled | 9/24/2020 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/23/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/23/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/23/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2019 | CELINA MORENO |
| Sewer availability | Cleared | 4/23/2019 | CELINA MORENO |
| Construction near power lines | Cleared | 5/3/2019 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/3/2019 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 5/3/2019 | BARTON HOLMES |
| Specific Plan | Cleared | 5/3/2019 | LATANYA ROUX |
| Low Impact Development | Cleared | 5/7/2019 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 5/7/2019 | JEANIE LAM |
Contact Information
| Contractor | Abraham Building & Consulting Inc; Lic. No.: 1046696-B | 5614 STANSBURY AVE SHERMAN OAKS, CA 91401 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2020 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 3/16/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2020 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/23/2020 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 3/27/2020 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/31/2020 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/10/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/12/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 5/12/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/12/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/13/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/29/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/29/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/29/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/3/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 6/8/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 6/10/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/12/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/15/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/15/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/15/2020 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 7/15/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/23/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/23/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/23/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/23/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/3/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 8/3/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| HVAC-Final | 8/3/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/3/2020 | Approved | HAMIK HARTOUNIAN |