1928 N DRACENA DR 90027
Certificate Information: 1928 N DRACENA DR 90027
- Application / Permit
- 19016-10000-11723
- Plan Check / Job No.
- B19LA08085
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL WOOD SHEAR WALL.
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Current Status
- CofC Issued on 12/16/2022
Permit Application Status History
| Submitted | 4/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2019 | EVERARDO SANTOS |
| Corrections Issued | 5/31/2019 | EVERARDO SANTOS |
| Quality Review Completed | 6/3/2019 | SAI KHUM |
| Plan Check Approved | 3/13/2020 | VARAND SARKISIAN |
| Issued | 9/21/2020 | APPLICANT |
| OK for CofC | 12/13/2022 | VAHE KELEDJIAN |
| CofC Issued | 12/16/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/14/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Zohar Construction Inc; Lic. No.: 852512-B | 12450 MAGNOLIA BLVD #4522 VALLEY VILLAGE, CA 91617 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/9/2020 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 10/16/2020 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 10/28/2020 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 11/10/2020 | Approved | MARK FERRARI |
| Final | 1/21/2021 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 1/21/2021 | Not Ready for Inspection | MARK FERRARI |
| Final | 4/23/2021 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 4/23/2021 | Approved | JONATHAN QUACH |
| Final | 12/13/2022 | OK for CofC | VAHE KELEDJIAN |