3651 S MCLAUGHLIN AVE 90066
Certificate Information: 3651 S MCLAUGHLIN AVE 90066
- Application / Permit
- 19016-10000-11589
- Plan Check / Job No.
- B19LA07993
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (6) SCCS & (1) MF.
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofC Issued on 3/2/2023
Permit Application Status History
| Submitted | 4/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2019 | JESSE VIDUYA |
| Corrections Issued | 5/28/2019 | JESSE VIDUYA |
| Quality Review Completed | 5/30/2019 | SAI KHUM |
| Applicant returned to address corrections | 12/16/2019 | JESSE VIDUYA |
| Plan Check Approved | 12/19/2019 | JESSE VIDUYA |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| OK for CofC | 2/21/2023 | ALAN NOVAK |
| CofC Issued | 3/2/2023 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/8/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Timmco Construction; Lic. No.: 960304-B | 700 SAN LUIS REY ROAD ARCADIA, CA 91007 |
| Engineer | Farmand,, Anthony E; Lic. No.: C62595 | 2372 MORSE AVE STE 137 IRVINE, CA 92614 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/22/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 11/22/2022 | Partial Approval | DAVID TSAU |
| Wood Frame | 11/30/2022 | Partial Approval | ALAN NOVAK |
| Wood Frame | 12/1/2022 | Partial Approval | ALAN NOVAK |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 1/10/2023 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 1/17/2023 | Approved | ALAN NOVAK |
| Reinforced Concrete Frame | 1/17/2023 | Approved | ALAN NOVAK |
| Reinforced Masonry Frame | 1/17/2023 | Approved | ALAN NOVAK |
| Deputy Steel/Welding | 1/18/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 1/19/2023 | Conditional Approval | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | ALAN NOVAK |
| Wood Frame | 1/20/2023 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 1/23/2023 | Approved | ALAN NOVAK |
| Final | 2/7/2023 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 2/7/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 2/21/2023 | OK for CofC | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 2/21/2023 | Approved | ALAN NOVAK |