7523 N ALABAMA AVE 91303
Certificate Information: 7523 N ALABAMA AVE 91303
- Application / Permit
- 19016-10000-11536
- Plan Check / Job No.
- B19LA07946
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC ChAPTER 93 USING 2 (N) OMF.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/21/2020
Permit Application Status History
| Submitted | 4/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2019 | JAIME OROZCO |
| Corrections Issued | 5/23/2019 | JAIME OROZCO |
| Quality Review Completed | 5/29/2019 | SAI KHUM |
| Building Plans Picked Up | 6/11/2019 | APPLICANT |
| Plan Check Approved | 12/27/2019 | JESSE VIDUYA |
| Issued | 2/18/2020 | LADBS |
| OK for CofC | 10/21/2020 | ERNESTO CORRAL |
| CofC Issued | 10/21/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/5/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Muradyan,, David; Lic. No.: S6232 | 10233 JOHANNA AVE SUNLAND, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2020 | Approved | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 3/12/2020 | Partial Inspection | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 3/13/2020 | Conditional Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 3/17/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 3/26/2020 | Conditional Approval | JONATHAN QUACH |
| Structural Steel Frame | 5/22/2020 | Conditional Approval | DANIEL VARNUM |
| Wood Frame | 5/22/2020 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 6/9/2020 | Conditional Approval | DANIEL VARNUM |
| Final | 6/25/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/25/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 6/25/2020 | Approved | DANIEL VARNUM |
| Final | 8/17/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Approved | DANIEL VARNUM |
| Final | 10/21/2020 | OK for CofC | ERNESTO CORRAL |