713 N BUNKER HILL AVE 90012
Certificate Information: 713 N BUNKER HILL AVE 90012
- Application / Permit
- 19016-10000-10904
- Plan Check / Job No.
- B19LA07523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 1 SCCS.
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofC Issued on 8/20/2020
Permit Application Status History
| Submitted | 4/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 5/15/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 5/16/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 5/21/2019 | APPLICANT |
| Applicant returned to address corrections | 7/10/2019 | CHUNG-WEN CHUANG |
| Plan Check Approved | 8/7/2019 | CHUNG-WEN CHUANG |
| Issued | 6/3/2020 | APPLICANT |
| OK for CofC | 8/11/2020 | VAHE KELEDJIAN |
| CofC Issued | 8/20/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 7/12/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 5/27/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 6/23/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 7/2/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 7/2/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/2/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 7/6/2020 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/10/2020 | Corrections Issued | MARK FERRARI |
| Final | 8/4/2020 | Partial Inspection | VAHE KELEDJIAN |
| METHANE-Final | 8/4/2020 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 8/4/2020 | Approved | VAHE KELEDJIAN |
| Final | 8/11/2020 | OK for CofC | VAHE KELEDJIAN |