8501 S SEPULVEDA BLVD 90045

Certificate Information: 8501 S SEPULVEDA BLVD 90045

Application / Permit
19016-10000-10654
Plan Check / Job No.
B19LA07375
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED EXTERIOR RENOVATION INCLUDING ROOF REPAIR, WINDOW & BALCONY SLIDER REPLACEMENT AND NEW WINDOWS. INTERIOR COMMON AREA RENOVATION (Building A )
Permit Issued
Issued on 12/7/2020
Issuing Office
Current Status
Permit Finaled on 3/16/2022

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 SARKIS HARABEDIAN
Corrections Issued 6/5/2019 SARKIS HARABEDIAN
Quality Review Completed 6/11/2019 ABDUL CHEGENI
Building Plans Picked Up 6/13/2019 APPLICANT
Disabled Access Plans Picked Up 6/14/2019 APPLICANT
Applicant returned to address corrections 8/27/2019 SARKIS HARABEDIAN
Green Plans Picked Up 11/9/2020 APPLICANT
Plan Check Approved 11/24/2020 SARKIS HARABEDIAN
Issued 12/7/2020 APPLICANT
Permit Finaled 3/15/2022 GRANT WOODS

Permit Application Clearance Information

Green Code Cleared 9/3/2019 SARAH ABOULHOSN
Fire Marshall Fire Life Safety Cleared 10/13/2020 ANDREW KO
DAS Clearance Cleared 10/29/2020 SARKIS HARABEDIAN
"Q" conditions Cleared 11/23/2020 ANACANY HURTADO
ZI Cleared 11/23/2020 ANACANY HURTADO

Contact Information

Architect Nakada,, Steven Mori; Lic. No.: C20605 550 SOUTH HOPE STREET SUITE 1740      LOS ANGELES, CA 90071
Contractor Vaughan Brendan Construction Inc; Lic. No.: 760613-B 480 WILBUR COURT      THOUSAND OAKS, CA 91360
Engineer Rubeiz,, Nadim Michel; Lic. No.: C69454 22711 CALIFA ST      WOODLAND HILLS, CA 91367

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2020 Approved ALAN NOVAK
Wood Frame 12/21/2020 Partial Approval ALAN NOVAK
Interior/Exterior Lathing 1/29/2021 Approved ALAN NOVAK
Drywall Nailing 3/23/2021 Partial Approval ALAN NOVAK
Footing/Foundation/Slab 4/8/2021 Partial Approval ALAN NOVAK
Footing/Foundation/Slab 5/7/2021 Approved ALAN NOVAK
Wood Frame 6/1/2021 Conditional Approval ALAN NOVAK
Final 12/23/2021 Not Ready for Inspection GRANT WOODS
Green Building Final 12/23/2021 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Approved GRANT WOODS
Smoke Detectors 12/23/2021 Not Ready for Inspection GRANT WOODS
Final 3/15/2022 Permit Finaled GRANT WOODS
Smoke Detectors 3/15/2022 Approved GRANT WOODS