1758 W 27TH ST 90018

Certificate Information: 1758 W 27TH ST 90018

Application / Permit
19016-10000-10464
Plan Check / Job No.
B19LA07246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND LAUNDRY ROOM TO "ADU" PER AB 494 & SB 229 AND PROVIDE 3 OPEN PARKING SPACES
Permit Issued
Issued on 4/23/2019
Issuing Office
Metro
Current Status
Issued on 4/23/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 JESSE JIMENEZ
Corrections Issued 4/11/2019 JESSE JIMENEZ
Issued 4/23/2019 LADBS

Permit Application Clearance Information

Address approval Cleared 4/11/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/11/2019 ROBYN STEELE
Sewer availability Cleared 4/11/2019 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/29/2019 Approved AJA COLLAY
Excavation/Setback/Form/Re-Bar 9/11/2019 Partial Approval RAUL BARAJAS
PLUMBING-Final 9/11/2019 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 9/18/2019 Partial Approval RICHARD STEINBACH
ELECTRICAL-Final 4/27/2020 No Access for Inspection KATHRYN BUTTERWORTH
Service/Power Release 4/27/2020 No Access for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 9/3/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/20/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/5/2022 Approved ADAM ESCOTO
PLUMBING-Final 2/23/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 5/27/2022 Approved STUART CHAPMAN
Insulation 11/30/2023 No Access for Inspection KATHRYN BUTTERWORTH
Drywall Nailing 12/1/2023 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 5/8/2024 Partial Approval ARTHUR NEGRETE
Insulation 5/8/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/8/2024 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Final 7/8/2024 Corrections Issued JOSEPH MCGARRY
Final 7/8/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/8/2024 Corrections Issued JOSEPH MCGARRY
Green Building Rough 7/8/2024 Approved JOSEPH MCGARRY
HVAC-Final 7/8/2024 Corrections Issued JOSEPH MCGARRY
METHANE-Final 7/8/2024 Approved JOSEPH MCGARRY
METHANE-Rough 7/8/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/8/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/22/2024 Approved JOSEPH MCGARRY
Final 7/22/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/22/2024 Not Ready for Inspection JOSEPH MCGARRY