1759 N WILTON PL 90028
Certificate Information: 1759 N WILTON PL 90028
- Application / Permit
- 19016-10000-10391
- Plan Check / Job No.
- B19LA07199
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 3 OMF.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/20/2026
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2019 | JESSE VIDUYA |
| Corrections Issued | 5/9/2019 | JESSE VIDUYA |
| Quality Review Completed | 5/9/2019 | SAI KHUM |
| Building Plans Picked Up | 5/15/2019 | APPLICANT |
| Plan Check Approved | 9/20/2019 | JESSE VIDUYA |
| Issued | 8/8/2023 | APPLICANT |
| OK for CofC | 11/7/2023 | JACOB MYERS |
| CofC Issued | 2/20/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/28/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Sturdy Builds Inc; Lic. No.: 1006879-B | 21300 VICTORY BLVD SUITE 635 WOODLAND HILLS, CA 91367 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/22/2023 | Partial Inspection | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 9/19/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Other (see comments) | 9/19/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Steel/Welding | 9/19/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 9/20/2023 | Approved | VAHE KELEDJIAN |
| Wood Frame | 9/20/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Structural Steel Frame | 9/22/2023 | Corrections Issued | VAHE KELEDJIAN |
| Wood Frame | 9/22/2023 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 9/27/2023 | Approved | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 10/12/2023 | Approved | VAHE KELEDJIAN |
| Final | 11/7/2023 | OK for CofC | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 11/7/2023 | Approved | JACOB MYERS |