610 S KINGSLEY DR 90005
Certificate Information: 610 S KINGSLEY DR 90005
- Application / Permit
- 19016-10000-10257
- Plan Check / Job No.
- B19LA07126
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Day Care Facility adults
- Work Description
- Change of use from pre-school daycare to adult daycare. Including demolition of (E) bearing partitions and new supporting beam and columns, new non-bearing partitions, new restrooms. New parking spaces and layout.
- Permit Issued
- Issued on 11/13/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | HELEN NGUYEN |
| Corrections Issued | 4/30/2019 | HELEN NGUYEN |
| Quality Review Completed | 5/7/2019 | FELIX FIGUEROA |
| Disabled Access Plans Picked Up | 5/7/2019 | APPLICANT |
| Building Plans Picked Up | 5/20/2019 | APPLICANT |
| Applicant returned to address corrections | 7/31/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/4/2019 | HELEN NGUYEN |
| Plan Check Approved | 10/23/2019 | HELEN NGUYEN |
| Issued | 11/13/2019 | LADBS |
| CofO in Progress | 1/21/2021 | EDWIN GREGORYONA |
| CofO Issued | 1/22/2021 | ERNESTO CORRAL |
| Permit Finaled | 1/22/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 9/4/2019 | ELENA LOPEZ |
| DAS Clearance | Cleared | 9/24/2019 | SHINE LIN |
| Project located in CRA area | Cleared | 9/24/2019 | JIM URQUHART |
| Fire Marshall Fire Life Safety | Cleared | 10/8/2019 | DOMINIQUE MEDINA |
Contact Information
| Architect | Nourani,, Shahab; Lic. No.: C26821 | 2451 ALISTER AVENUE TUSTIN, CA 92782 |
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 2/5/2020 | No Access for Inspection | GRANT WOODS |
| Wood Frame | 2/6/2020 | Corrections Issued | GRANT WOODS |
| Drywall Nailing | 3/26/2020 | Approved | EDWIN GREGORYONA |
| Final | 9/18/2020 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Final | 9/18/2020 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2020 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 9/18/2020 | Approved | EDWIN GREGORYONA |
| Final | 10/15/2020 | Conditional Approval | EDWIN GREGORYONA |
| Final | 1/12/2021 | Conditional Approval | EDWIN GREGORYONA |