18412 W OXNARD ST 91356

Certificate Information: 18412 W OXNARD ST 91356

Application / Permit
19016-10000-10239
Plan Check / Job No.
B19LA07111
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Core and shell work which includes exterior alterations, structural roof work, new skylights, new restrooms, and disabled access parking striping and remove infill between buildings (between 18408 & 18412 W Oxnard St) to create two separate buildings and parking analysis to establish required parking per current code (Bldg. 2).
Permit Issued
Issued on 9/5/2019
Issuing Office
Metro
Current Status
CofO Corrected on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Green Plans Picked Up 4/23/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 RODOLFO ARIAS
Disabled Access Plans Picked Up 4/29/2019 APPLICANT
Corrections Issued 4/30/2019 RODOLFO ARIAS
Quality Review Completed 5/3/2019 GARO TELMI
Building Plans Picked Up 5/3/2019 APPLICANT
Applicant returned to address corrections 6/13/2019 RODOLFO ARIAS
Applicant returned to address corrections 6/19/2019 RODOLFO ARIAS
Applicant returned to address corrections 6/28/2019 RODOLFO ARIAS
Applicant returned to address corrections 7/1/2019 RODOLFO ARIAS
Applicant returned to address corrections 7/5/2019 RODOLFO ARIAS
Applicant returned to address corrections 7/12/2019 RODOLFO ARIAS
Applicant returned to address corrections 8/7/2019 RODOLFO ARIAS
Applicant returned to address corrections 8/13/2019 RODOLFO ARIAS
Plan Check Approved 8/21/2019 RODOLFO ARIAS
Issued 9/5/2019 LADBS
CofO in Progress 6/7/2022 ANDREW DORSO
CofO Issued-Status Void 6/14/2022 RICKEY JACKSON
Permit Finaled-Status Void 6/14/2022 RICKEY JACKSON
Re-Activate Permit 9/8/2022 JEFFREY DURAN
CofO Corrected 9/8/2022 JEFFREY DURAN
Permit Finaled 9/8/2022 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 5/16/2019 ANNA VAN
Roof/Waste drainage to street Cleared 5/16/2019 ZIXUAN CHEN
Sewer availability Cleared 5/16/2019 ZIXUAN CHEN
DAS Clearance Cleared 7/29/2019 RODOLFO ARIAS
Eng Process Fee Ord 176,300 Cleared 8/7/2019 ADRIAN SANCHEZ
Green Code Cleared 8/8/2019 RODOLFO ARIAS

Contact Information

Architect Rakestraw,, Thomas Evan; Lic. No.: C19790 515 EL MODENA AVENUE      NEWPORT BEACH, CA 92663
Contractor Smith And Severson Builders Llc; Lic. No.: 989943-B 21072 BAKE PARKWAY SUITE 106      LAKE FOREST, CA 92630
Engineer Thompson,, Douglas Sevier; Lic. No.: S2578 21084 BAKE PARKWAY SUITE 100      LAKE FOREST, CA 92630

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 10/3/2019 Approved DANIEL VARNUM
Footing/Foundation/Slab 11/4/2019 Approved DANIEL VARNUM
Wood Frame 11/13/2019 Approved DANIEL VARNUM
Interior/Exterior Lathing 11/25/2019 Approved DANIEL VARNUM
Final 2/15/2022 OK to Expire Permit CAMERON CHABAN
Green Building Final 2/15/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Approved CAMERON CHABAN
Smoke Detectors 2/15/2022 Approved CAMERON CHABAN
Final 5/3/2022 Not Ready for Inspection ANDREW DORSO
Final 5/13/2022 OK to Issue CofO ANDREW DORSO