3605 S STEPHEN M WHITE DR 90731

Certificate Information: 3605 S STEPHEN M WHITE DR 90731

Application / Permit
19016-10000-10189
Plan Check / Job No.
B19LA07091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93 USING 2 SCCS.
Permit Issued
Issued on 1/27/2020
Issuing Office
Metro
Current Status
CofC Issued on 11/13/2020

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 5/1/2019 THOMAS SHERMAN
Corrections Issued 5/6/2019 THOMAS SHERMAN
Quality Review Completed 5/6/2019 SAI KHUM
Building Plans Picked Up 5/10/2019 APPLICANT
Plan Check Approved 6/19/2019 THOMAS SHERMAN
Issued 1/27/2020 LADBS
OK for CofC 11/10/2020 JOEY BUCHANAN
CofC Issued 11/13/2020 NICK LAROCCA

Permit Application Clearance Information

Housing rent stabilization Cleared 1/27/2020 CHARLES GARCIA

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2020 Corrections Issued JOEY BUCHANAN
Deputy Drilled-In Anchors 2/19/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 2/19/2020 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 2/24/2020 Conditional Approval JOEY BUCHANAN
Footing/Foundation/Slab 2/24/2020 Conditional Approval JOEY BUCHANAN
Structural Steel Frame 2/24/2020 Conditional Approval JOEY BUCHANAN
Wood Frame 2/24/2020 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 2/26/2020 Approved JOEY BUCHANAN
Structural Steel Frame 3/2/2020 Approved JOEY BUCHANAN
Wood Frame 3/2/2020 Approved JOEY BUCHANAN
Drywall Nailing 3/5/2020 Approved JOEY BUCHANAN
Interior/Exterior Lathing 3/5/2020 Corrections Issued JOEY BUCHANAN
Final 3/25/2020 Corrections Issued JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 3/25/2020 SGSOV Not Ready JOEY BUCHANAN
Smoke Detectors 3/25/2020 Not Ready for Inspection JOEY BUCHANAN
Final 11/4/2020 Corrections Issued JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 11/4/2020 Not Ready for Inspection JOEY BUCHANAN
Final 11/10/2020 OK for CofC JOEY BUCHANAN