3605 S STEPHEN M WHITE DR 90731
Certificate Information: 3605 S STEPHEN M WHITE DR 90731
- Application / Permit
- 19016-10000-10189
- Plan Check / Job No.
- B19LA07091
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 2 SCCS.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/13/2020
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2019 | THOMAS SHERMAN |
| Corrections Issued | 5/6/2019 | THOMAS SHERMAN |
| Quality Review Completed | 5/6/2019 | SAI KHUM |
| Building Plans Picked Up | 5/10/2019 | APPLICANT |
| Plan Check Approved | 6/19/2019 | THOMAS SHERMAN |
| Issued | 1/27/2020 | LADBS |
| OK for CofC | 11/10/2020 | JOEY BUCHANAN |
| CofC Issued | 11/13/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/27/2020 | CHARLES GARCIA |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2020 | Corrections Issued | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 2/19/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 2/19/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 2/24/2020 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/24/2020 | Conditional Approval | JOEY BUCHANAN |
| Structural Steel Frame | 2/24/2020 | Conditional Approval | JOEY BUCHANAN |
| Wood Frame | 2/24/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 2/26/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 3/2/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/2/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 3/5/2020 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 3/5/2020 | Corrections Issued | JOEY BUCHANAN |
| Final | 3/25/2020 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2020 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 3/25/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 11/4/2020 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/4/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 11/10/2020 | OK for CofC | JOEY BUCHANAN |
| Smoke Detectors | 11/10/2020 | Approved | JOEY BUCHANAN |