916 N HUDSON AVE 90038
Certificate Information: 916 N HUDSON AVE 90038
- Application / Permit
- 19016-10000-10158
- Plan Check / Job No.
- B19LA07052
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93 USING 4 NEW SCCS
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofC Issued on 6/7/2022
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2019 | JESSE VIDUYA |
| Corrections Issued | 5/3/2019 | JESSE VIDUYA |
| Quality Review Completed | 5/3/2019 | SAI KHUM |
| Building Plans Picked Up | 5/7/2019 | APPLICANT |
| Plan Check Approved | 5/22/2019 | JESSE VIDUYA |
| Issued | 1/28/2022 | APPLICANT |
| OK for CofC | 6/7/2022 | BRUCE CAMPBELL |
| CofC Issued | 6/7/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/26/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Sturdy Builds Inc; Lic. No.: 1006879-B | 21300 VICTORY BLVD SUITE 635 WOODLAND HILLS, CA 91367 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/14/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 4/27/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 4/27/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 5/2/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 5/6/2022 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 5/6/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 5/6/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 5/11/2022 | Corrections Issued | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 5/16/2022 | Approved | BRUCE CAMPBELL |
| Final | 5/25/2022 | Corrections Issued | BRUCE CAMPBELL |
| METHANE-Final | 5/25/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 5/25/2022 | Corrections Issued | BRUCE CAMPBELL |
| Final | 6/7/2022 | OK for CofC | BRUCE CAMPBELL |
| Smoke Detectors | 6/7/2022 | Approved | BRUCE CAMPBELL |