417 N ARDMORE AVE 90004

Certificate Information: 417 N ARDMORE AVE 90004

Application / Permit
19016-10000-09589
Plan Check / Job No.
B19LA06763
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 4 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
Permit Issued
Issued on 3/12/2020
Issuing Office
Metro
Current Status
CofC Issued on 12/2/2020

Permit Application Status History

Submitted 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 ERWIN PASCUA
Corrections Issued 5/5/2019 ERWIN PASCUA
Quality Review Completed 5/8/2019 SAI KHUM
Building Plans Picked Up 6/3/2019 APPLICANT
Plan Check Approved 8/16/2019 ERWIN PASCUA
Issued 3/12/2020 LADBS
OK for CofC 11/30/2020 MARK FERRARI
CofC Issued 12/2/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 2/27/2020 MICHAEL GREGERSON

Contact Information

Contractor D And M General Constructor Inc; Lic. No.: 745510-B 6520 PLATT AVE #551      WEST HILLS, CA 91307
Engineer Farmand,, Anthony E; Lic. No.: C62595 2372 MORSE AVE STE 137      IRVINE, CA 92614

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2020 Corrections Issued MARK FERRARI
Special/Order Compliance 4/14/2020 Partial Inspection JOE VELASQUEZ
Excavation/Setback/Form/Re-Bar 4/17/2020 Not Ready for Inspection MARK FERRARI
Pre-Inspection 4/17/2020 Corrections Issued MARK FERRARI
Deputy Steel/Welding 5/12/2020 Conditional Approval FRED WOHLFARTH
Deputy Reinf. Concrete 6/8/2020 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 6/8/2020 Not Ready for Inspection FELIX CEBALLOS
Footing/Foundation/Slab 6/9/2020 Approved FELIX CEBALLOS
Structural Steel Frame 6/24/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 6/24/2020 Corrections Issued MARK FERRARI
Wood Frame 7/14/2020 Approved MARK FERRARI
Interior/Exterior Lathing 8/18/2020 Corrections Issued MARK FERRARI
Final 10/15/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 10/15/2020 Not Ready for Inspection MARK FERRARI
Final 11/9/2020 Not Ready for Inspection JONATHAN QUACH
Smoke Detectors 11/9/2020 Not Ready for Inspection JONATHAN QUACH
Final 11/12/2020 Conditional Approval JONATHAN QUACH
Smoke Detectors 11/12/2020 Approved JONATHAN QUACH
Final 11/30/2020 OK for CofC MARK FERRARI