1322 3/4 S 5TH AVE 90019

Certificate Information: 1322 3/4 S 5TH AVE 90019

Application / Permit
19016-10000-09583
Plan Check / Job No.
B19LA06756
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to accessory dwelling unit (ADU)
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 2/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 TU HUA
Corrections Issued 5/15/2019 TU HUA
Quality Review Completed 5/28/2019 MINYE PAK
Applicant returned to address corrections 2/24/2021 TU HUA
Applicant returned to address corrections 9/21/2021 TU HUA
Plan Check Approved 9/28/2021 TU HUA
Issued 12/1/2021 APPLICANT
Building Plans Picked Up 12/8/2021 APPLICANT
CofO in Progress 2/12/2026 BRENDAN MORELLI
Permit Finaled 2/13/2026 DEROLD HAUFF
CofO Issued 2/13/2026 DEROLD HAUFF
Permit Finaled 2/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 3/22/2021 RICHARD REASER
ZA Case Cleared 3/22/2021 RICHARD REASER
Address approval Cleared 4/5/2021 WALLIE JONG
Sewer availability Cleared 4/5/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/6/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 7/8/2021 KYLE WINSTON
ZI Cleared 7/8/2021 KYLE WINSTON

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 2/3/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/3/2023 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/26/2023 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 12/26/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 1/22/2024 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 1/22/2024 Partial Inspection ARTHUR NEGRETE
PLUMBING-Rough 1/22/2024 Approved ARTHUR NEGRETE
Insulation 1/24/2024 Approved ARTHUR NEGRETE
Drywall Nailing 1/29/2024 Approved ARTHUR NEGRETE
Final 11/14/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 11/14/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Final 11/14/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 11/14/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 11/14/2024 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 11/15/2024 No Access for Inspection ARTHUR NEGRETE
PLUMBING-Final 11/15/2024 No Access for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 2/12/2025 Corrections Issued NICHOLAS LOPEZ
Final 2/12/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 2/12/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 2/12/2025 Corrections Issued NICHOLAS LOPEZ
METHANE-Final 2/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 2/12/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 2/12/2025 Approved NICHOLAS LOPEZ
Final 2/18/2025 Partial Approval ARTHUR NEGRETE
Green Building Final 2/18/2025 Approved ARTHUR NEGRETE
METHANE-Final 2/18/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 2/20/2025 Approved ARTHUR NEGRETE
HVAC-Final 2/20/2025 Approved ARTHUR NEGRETE
HVAC-Final 4/11/2025 Approved ARTHUR NEGRETE
Final 2/12/2026 OK to Issue CofO BRENDAN MORELLI