502 N MCDONALD AVE 90744

Certificate Information: 502 N MCDONALD AVE 90744

Application / Permit
19016-10000-09502
Plan Check / Job No.
B19LA06694
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ***"COMPLY WITH DEPARTMENT ORDER effective date 03/15/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/14/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 10/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 4/3/2019 CHIHARU SUZUKI
Corrections Issued 4/3/2019 CHIHARU SUZUKI
Applicant returned to address corrections 5/22/2019 MINA HABIB
Plan Check Approved 6/4/2019 SINA KHOSRAVI
Issued 8/14/2019 LADBS
CofO in Progress 10/16/2020 BRIAN CHRISTIAN
Permit Finaled 10/16/2020 BRUCE TODD
CofO Issued 10/16/2020 BRUCE TODD
Permit Finaled 10/16/2020 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 5/22/2019 CELINA MORENO
Clean Up Green Up Cleared 5/22/2019 SARAHI ORTEGA
Eng Process Fee Ord 176,300 Cleared 5/22/2019 JEANIE LAM
Sewer availability Cleared 5/22/2019 JEANIE LAM
ZA Case Cleared 5/22/2019 SARAHI ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2019 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 9/11/2019 Not Ready for Inspection BRIAN CHRISTIAN
Pre-Inspection 10/16/2019 Not Ready for Inspection BRIAN CHRISTIAN
Excavation/Setback/Form/Re-Bar 11/18/2019 Approved BRIAN CHRISTIAN
Excavation/Setback/Form/Re-Bar 12/11/2019 Partial Approval BRIAN CHRISTIAN
Deputy Reinf. Concrete 12/12/2019 Conditional Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 1/6/2020 Corrections Issued BRIAN CHRISTIAN
BUILDING-Rough-Frame 2/10/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 2/10/2020 Not Ready for Inspection BRIAN CHRISTIAN
PLUMBING-Rough 2/10/2020 Approved BRIAN CHRISTIAN
Deputy Drilled-In Anchors 2/13/2020 Conditional Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 2/14/2020 Conditional Approval BRIAN CHRISTIAN
Insulation 2/19/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 2/20/2020 Conditional Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 3/10/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 3/10/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 3/10/2020 Approved BRIAN CHRISTIAN
Final 4/10/2020 Corrections Issued ANDREW BEELI
METHANE-Final 4/10/2020 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 4/10/2020 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 4/10/2020 Approved ANDREW BEELI
ELECTRICAL-Final 4/15/2020 Approved BRIAN CHRISTIAN
METHANE-Final 4/15/2020 Approved BRIAN CHRISTIAN
PLUMBING-Final 4/15/2020 Partial Approval BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 4/15/2020 SGSOV Not Ready BRIAN CHRISTIAN
Sewer 4/15/2020 Approved BRIAN CHRISTIAN
Final 4/16/2020 Partial Approval BRIAN CHRISTIAN
Gas Test 4/16/2020 Approved BRIAN CHRISTIAN
HVAC-Final 4/16/2020 Approved BRIAN CHRISTIAN
PLUMBING-Final 4/16/2020 Approved BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 4/16/2020 SGSOV Approved BRIAN CHRISTIAN
Final 10/16/2020 OK to Issue CofO BRIAN CHRISTIAN