9000 N WINNETKA AVE 91324
Certificate Information: 9000 N WINNETKA AVE 91324
- Application / Permit
- 19016-10000-08987
- Plan Check / Job No.
- B19LA06389
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Hydroponic Agricultural Enterprise
- Work Description
- CHANGE OF USE FROM MANUFACTURING/WAREHOUSE TO MANUFACTURING, CULTIVATION/GROWING (F-1) FACILITY. TOTAL TENANT IMPROVEMENT FLOOR AREA OF 23,200 SF. RESTRIPING (E) PARKING
- Permit Issued
- Issued on 7/5/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2019 | APPLICANT |
| Green Plans Picked Up | 4/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | JEFFREY MACHADO |
| Corrections Issued | 4/22/2019 | JEFFREY MACHADO |
| Quality Review Completed | 4/30/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 5/1/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 5/17/2019 | APPLICANT |
| Applicant returned to address corrections | 5/20/2019 | DEAN RYAN REYES |
| Applicant returned to address corrections | 5/21/2019 | DEAN RYAN REYES |
| Plan Check Approved | 7/2/2019 | JEFFREY MACHADO |
| Issued | 7/5/2019 | LADBS |
| TCO Issued (Expire Date: 06-27-2021) | 12/29/2020 | JEFFREY DURAN |
| TCO Issued (Expire Date: 12-22-2021) | 6/25/2021 | JEFFREY DURAN |
| CofO in Progress | 9/3/2021 | JEFFREY DURAN |
| Permit Finaled | 9/3/2021 | JEFFREY DURAN |
| CofO Issued | 9/3/2021 | JEFFREY DURAN |
| Permit Finaled | 9/3/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/17/2019 | LATANYA ROUX |
| ZA Case | Cleared | 5/17/2019 | LATANYA ROUX |
| Green Code | Cleared | 6/3/2019 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2019 | JEANIE LAM |
| Sewer availability | Cleared | 6/18/2019 | JEANIE LAM |
| DAS Clearance | Cleared | 6/27/2019 | JEFFREY MACHADO |
| Fire Marshall Fire Life Safety | Cleared | 7/2/2019 | WILLIAM JOHNS |
Contact Information
| Architect | Cho,, Leo D; Lic. No.: C25658 | GRACE PARTNERSHIP INC. 550 S. WILTON PL. LOS ANGELES, CA 90020 |
| Contractor | Millennia Construction; Lic. No.: 931496-B | 1156 5TH AVENUE LOS ANGELES, CA 90019 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Sarujikamjornwattana,, Phaitoon; Lic. No.: S4850 | 7069 E HANBURY ST LONG BEACH, CA 90808 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 8/27/2019 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 8/27/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 8/27/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 8/30/2019 | Partial Approval | MILLARD ARDOIN |
| Structural Steel Frame | 8/30/2019 | Partial Approval | MILLARD ARDOIN |
| Insulation | 9/9/2019 | Partial Approval | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 10/15/2019 | Not Ready for Inspection | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 10/28/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 10/29/2019 | Approved | MILLARD ARDOIN |
| Deputy Reinf. Concrete | 10/30/2019 | Approved | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 11/6/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/7/2019 | Not Ready for Inspection | MILLARD ARDOIN |
| Drywall Nailing | 12/9/2019 | Not Ready for Inspection | MILLARD ARDOIN |
| Pre-Inspection | 12/9/2019 | Partial Inspection | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 12/11/2019 | Approved | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 1/21/2020 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 1/22/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 5/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 5/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 5/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 5/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 5/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 6/30/2020 | Partial Inspection | JEFFREY FULTON |
| Green Building Final | 6/30/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 6/30/2020 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 6/30/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 6/30/2020 | Not Ready for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 7/31/2020 | Corrections Issued | JEFFREY FULTON |
| Special/Order Compliance | 8/21/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 8/26/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 11/30/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 12/8/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 12/8/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/8/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 12/8/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 12/8/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 12/18/2020 | Corrections Issued | JEFFREY FULTON |
| Final | 12/23/2020 | Partial Inspection | JEFFREY FULTON |
| Green Building Final | 12/23/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/23/2020 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Special/Order Compliance | 6/3/2021 | No Access for Inspection | JEFFREY FULTON |
| Final | 6/30/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 6/30/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Final | 7/9/2021 | Corrections Issued | JEFFREY FULTON |
| Green Building Final | 7/9/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV No Gas | JEFFREY FULTON |
| Final | 9/3/2021 | OK to Issue CofO | JEFFREY DURAN |
| Smoke Detectors | 9/3/2021 | Approved | JEFFREY DURAN |