1822 N NORTH BROADWAY 90031
Certificate Information: 1822 N NORTH BROADWAY 90031
- Application / Permit
- 19016-10000-08935
- Plan Check / Job No.
- B19LA06361
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE TO GROUND LEVEL OF AN EXISTING 2 STORY BUILDING TO RESTAURANT WITH OPEN PATIO AREA
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | ERIC WONG |
| Corrections Issued | 4/18/2019 | ERIC WONG |
| Green Plans Picked Up | 4/19/2019 | APPLICANT |
| Quality Review Completed | 4/23/2019 | LAURA DUONG |
| Building Plans Picked Up | 4/24/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 5/14/2019 | APPLICANT |
| Applicant returned to address corrections | 7/25/2019 | ERIC WONG |
| Plan Check Approved | 12/20/2019 | ERIC WONG |
| Issued | 1/6/2020 | LADBS |
Permit Application Clearance Information
| Permit | Cleared | 5/28/2019 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 6/17/2019 | ERIK BEASLEY |
| Food Service Establishment | Cleared | 7/12/2019 | RAMESHBHAIR PATEL |
| Green Code | Cleared | 7/16/2019 | SARAH ABOULHOSN |
| DAS Clearance | Cleared | 7/23/2019 | EDDIE GARIN |
| Specific Plan | Cleared | 7/23/2019 | MICHAEL SIN |
| ZA Case | Cleared | 7/24/2019 | ANNA VAN |
| Food establishment approval | Cleared | 7/25/2019 | LACDHS APPROVED |
| Bicycle Parking | Cleared | 12/16/2019 | JAMES KHO |
Contact Information
| Contractor | Clc Builders Inc; Lic. No.: 580175-B | 22916 ELKWOOD STREET WEST HILLS, CA 91304 |
| Engineer | Chiu,, Frankie Wai-King; Lic. No.: C43852 | 5132 CROWN AVE LA CANADA, CA 91011 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/12/2020 | Approved | RONALD PACHECO |
| Footing/Foundation/Slab | 2/12/2020 | Partial Approval | RONALD PACHECO |
| Wood Frame | 3/6/2020 | Conditional Approval | RONALD PACHECO |
| Final | 3/23/2020 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 3/23/2020 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 3/23/2020 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 3/23/2020 | Not Ready for Inspection | RONALD PACHECO |
| Light Gage Steel Frame | 4/1/2020 | Conditional Approval | RONALD PACHECO |
| Wood Frame | 4/1/2020 | Conditional Approval | RONALD PACHECO |
| Special/Order Compliance | 4/30/2020 | Partial Inspection | RONALD PACHECO |
| Drywall Nailing | 5/6/2020 | Approved | RONALD PACHECO |
| T-Bar Ceiling | 6/2/2020 | Conditional Approval | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 6/5/2020 | Approved | RONALD PACHECO |
| Final | 6/9/2020 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 6/9/2020 | Approved | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 6/9/2020 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 6/9/2020 | Approved | RONALD PACHECO |
| Final | 7/1/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 7/7/2020 | Not Ready for Inspection | LANNY MERRICK |
| Pre-Inspection | 7/8/2020 | Partial Inspection | RONALD PACHECO |
| Final | 9/22/2022 | Partial Inspection | MARK FERRARI |
| Special/Order Compliance | 4/30/2024 | Corrections Issued | RONALD JIMENEZ |