4579 W AMBROSE AVE 90027
Certificate Information: 4579 W AMBROSE AVE 90027
- Application / Permit
- 19016-10000-08678
- Plan Check / Job No.
- B19LA06159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 7/29/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/2/2020
Permit Application Status History
| Submitted | 8/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2019 | MANUEL MONTUFAR |
| Corrections Issued | 9/19/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 9/25/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/27/2020 | MANUEL MONTUFAR |
| Issued | 7/29/2020 | APPLICANT |
| OK for CofC | 10/30/2020 | MARK FERRARI |
| CofC Issued | 11/2/2020 | TERRY HERR |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/27/2020 | STEVEN HOFSTAD |
Contact Information
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: NA71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2020 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/1/2020 | Partial Approval | FELIX CEBALLOS |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 9/3/2020 | Approved | FELIX CEBALLOS |
| Deputy Wood Construction | 9/21/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 9/23/2020 | Approved | MARK FERRARI |
| Wood Frame | 9/23/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 10/20/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 10/22/2020 | Approved | MARK FERRARI |
| Final | 10/30/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 10/30/2020 | Approved | MARK FERRARI |