5024 N MONTE BONITO DR 90041

Certificate Information: 5024 N MONTE BONITO DR 90041

Application / Permit
19016-10000-08640
Plan Check / Job No.
B19LA06130
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) BEDROOM AND (E) STUDY ROOM INTO A (N) BATHROOM, ADD 2 (N) BEDROOMS AND 1 (N) BATHROOM IN EXISTING ATTIC SPACE. (SEE COMMENTS)
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 2/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2019 APPLICANT
Assigned to Plan Check Engineer 3/27/2019 AUNG SOE
Corrections Issued 3/27/2019 AUNG SOE
Applicant returned to address corrections 11/8/2019 JOHNNY WU
Applicant returned to address corrections 2/7/2020 JOHNNY WU
Plan Check Approved 3/2/2020 JOHNNY WU
Issued 1/25/2021 APPLICANT
CofO in Progress 2/16/2022 CRAIG VAUGHAN
Permit Finaled 2/25/2022 DEROLD HAUFF
CofO Issued 2/25/2022 DEROLD HAUFF
Permit Finaled 2/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/27/2019 ERIK BEASLEY
Sewer availability Cleared 3/27/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 12/17/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 12/17/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 12/17/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/17/2019 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 2/20/2020 KIRK LINKLATER

Contact Information

Contractor Watchful Eye Project Management; Lic. No.: 1039729-B 33125 N 81ST STREET      SCOTTSDALE, AZ 85266
Engineer Esparza,, Jesus T; Lic. No.: C19990 6107 YORK BLVD      LOS ANGELES, CA 90042
Engineer Wong,, Jim Chu Man; Lic. No.: C69393 PO BOX 373      GLENDORA, CA 91740
Engineer Zhang,, Zhiqiang; Lic. No.: M34617 705 LOS OLIVOS DR      SAN GABRIEL, CA 91775

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/22/2021 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/22/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/27/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 5/27/2021 Approved COREY HUPP
Wood Frame 5/27/2021 Approved COREY HUPP
ELECTRICAL-Rough 6/4/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/15/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 6/15/2021 Approved CRAIG VAUGHAN
HVAC-Rough 6/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Insulation 6/15/2021 Approved CRAIG VAUGHAN
Shower Pan 6/15/2021 Approved CRAIG VAUGHAN
Smoke Detectors 6/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/15/2021 Approved CRAIG VAUGHAN
Drywall Nailing 7/1/2021 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 10/5/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 10/5/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/5/2021 Approved CRAIG VAUGHAN
Green Building Rough 10/5/2021 Approved CRAIG VAUGHAN
MERV13>=Final 10/5/2021 Approved CRAIG VAUGHAN
MERV13>=Rough 10/5/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/5/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/16/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/16/2022 Approved CRAIG VAUGHAN
Final 2/16/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 2/16/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 2/16/2022 Approved CRAIG VAUGHAN
Special/Order Compliance 2/16/2022 Partial Inspection AMY COLIN