7252 N MILWOOD AVE 91303
Certificate Information: 7252 N MILWOOD AVE 91303
- Application / Permit
- 19016-10000-08522
- Plan Check / Job No.
- B19LA06064
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93 USING HARDY PANEL AND WOOD SHEAR WALLS
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/17/2023
Permit Application Status History
| Submitted | 3/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2019 | VARAND SARKISIAN |
| Corrections Issued | 4/26/2019 | VARAND SARKISIAN |
| Quality Review Completed | 4/30/2019 | SAI KHUM |
| Building Plans Picked Up | 9/16/2019 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | VARAND SARKISIAN |
| Plan Check Approved | 9/3/2020 | VARAND SARKISIAN |
| Issued | 5/3/2022 | APPLICANT |
| OK for CofC | 4/3/2023 | KENNETH ROBERTS |
| CofC Issued | 8/17/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/14/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Seismic Retrofit Specialists; Lic. No.: 549884-B | 11949 JEFFERSON BLVD STE 105 CULVER CITY, CA 90230 |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 19900 ACRE ST LOS ANGELES, CA 91324 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2022 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 1/6/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Structural Steel Frame | 1/6/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Wood Frame | 1/6/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 2/21/2023 | Conditional Approval | KENNETH ROBERTS |
| Special/Order Compliance | 2/23/2023 | Approved | BRIAN KELLY |
| Wall Anchors | 2/23/2023 | Approved | KENNETH ROBERTS |
| Wood Frame | 2/23/2023 | Partial Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 2/27/2023 | Conditional Approval | KENNETH ROBERTS |
| Deputy Wood Construction | 2/28/2023 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 3/2/2023 | Approved | KENNETH ROBERTS |
| Special/Order Compliance | 3/2/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Structural Steel Frame | 3/2/2023 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 3/7/2023 | Partial Inspection | JEFFREY FULTON |
| Special/Order Compliance | 3/7/2023 | Partial Approval | STEVEN LEVITT |
| Final | 3/23/2023 | Corrections Issued | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 3/23/2023 | Approved | KENNETH ROBERTS |
| Final | 4/3/2023 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | KENNETH ROBERTS |