5815 W OLYMPIC BLVD 90036
Certificate Information: 5815 W OLYMPIC BLVD 90036
- Application / Permit
- 19016-10000-08480
- Plan Check / Job No.
- B19LA06037
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 2 (N) SCCS.
- Permit Issued
- Issued on 1/28/2021
- Issuing Office
- Current Status
- CofC Issued on 6/7/2021
Permit Application Status History
| Submitted | 3/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/25/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/25/2019 | SAI KHUM |
| Building Plans Picked Up | 5/7/2019 | APPLICANT |
| Plan Check Approved | 7/25/2019 | CHUNG-WEN CHUANG |
| Issued | 1/28/2021 | APPLICANT |
| OK for CofC | 5/10/2021 | DARRYL ARNOLD |
| CofC Issued | 6/7/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| HPOZ | Cleared | 7/15/2019 | CHRISTINA PARK |
| Housing rent stabilization | Cleared | 1/6/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Parthenon Structures Inc; Lic. No.: 1056070-B | 3300 FOOTHILL BLVD #8601 LA CRESCENTA, CA 91214 |
| Engineer | Hagopyan,, Edmond; Lic. No.: C80143 | 7939 WENTWORTH STREET SUNLAND, CA 91040 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/19/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/5/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/30/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 3/30/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 3/30/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/31/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 4/6/2021 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 4/28/2021 | Approved | DARRYL ARNOLD |
| Final | 5/10/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 5/10/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/10/2021 | Approved | DARRYL ARNOLD |