14813 W DELANO ST 91411
Certificate Information: 14813 W DELANO ST 91411
- Application / Permit
- 19016-10000-07932
- Plan Check / Job No.
- B19LA05661
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/11/2021
Permit Application Status History
| Submitted | 3/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2019 | MANUEL MONTUFAR |
| Corrections Issued | 4/2/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 4/3/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 4/9/2019 | APPLICANT |
| Plan Check Approved | 4/16/2019 | MANUEL MONTUFAR |
| Issued | 3/18/2020 | LADBS |
| OK for CofC | 12/29/2020 | MARK FERRARI |
| CofC Issued | 1/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/28/2020 | MICHAEL GREGERSON |
Contact Information
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/7/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/7/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/8/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/10/2020 | Conditional Approval | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 7/10/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 7/10/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Insulation | 7/10/2020 | Approved | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 7/13/2020 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/13/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 7/13/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/15/2020 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/24/2020 | Approved | JOE VELASQUEZ |
| Final | 8/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 8/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 12/29/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 12/29/2020 | Approved | MARK FERRARI |