7323 N MILWOOD AVE 91303
Certificate Information: 7323 N MILWOOD AVE 91303
- Application / Permit
- 19016-10000-07554
- Plan Check / Job No.
- B19LA05410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL ONE (N) CANILEVER COLUMN AND TWO (N) SHEAR WALLS
- Permit Issued
- Issued on 3/13/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/23/2021
Permit Application Status History
| Submitted | 3/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | EVERARDO SANTOS |
| Corrections Issued | 4/18/2019 | EVERARDO SANTOS |
| Quality Review Completed | 4/18/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 4/26/2019 | APPLICANT |
| Applicant returned to address corrections | 9/10/2019 | EVERARDO SANTOS |
| Plan Check Approved | 9/16/2019 | EVERARDO SANTOS |
| Issued | 3/13/2020 | LADBS |
| OK for CofC | 10/25/2021 | KENNETH ROBERTS |
| CofC Issued | 12/23/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/10/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Samama Albert; Lic. No.: 557517-B | 22487 LIBERTY BELL RD CALABASAS, CA 91302 |
| Engineer | Samama,, Albert; Lic. No.: C43288 | 22487 LIBERTY BELL RD CALABASAS, CA 91302 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2020 | Partial Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 6/11/2020 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 6/11/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 6/11/2020 | Approved | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 6/23/2020 | Conditional Approval | DANIEL VARNUM |
| Wood Frame | 6/23/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 7/8/2020 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 8/10/2020 | Approved | HAMID PISHEHVAR |
| Final | 4/28/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 4/28/2021 | Approved | DANIEL VARNUM |
| Final | 10/25/2021 | OK for CofC | KENNETH ROBERTS |